A company employed 200 workers to complete a certain work in 150 days. If only one- fourth of the work has been done in 50 days, then in order to complete the whole work in time, the number of additional workers to be employed was

Asked on by | Votes 0 | Views: 180 | Tags: time and work     | quantitative aptitude     | ssc cgl tier 2 2015     | Add Bounty

A company employed 200 workers to complete a certain work in 150 days. If only one- fourth of the work has been done in 50 days, then in order to complete the whole work in time, the number of additional workers to be employed was
1). 100
2). 300
3). 600
4). 200


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

2 vote
Answered by on | Votes 2 |
is option 1 is the correct answer?? am i right?

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (4+5)
Submit:

Other Questions

1. A, B and C can complete a piece of work in 24, 6 and 12 days respectively. Working together, they will complete the same work in

2. Three persons undertake to complete a piece of work for Rs. 1,200. The first person complete the work in 8 days, second person in 12 days and third person in 16 days.They complete the work with the help of a fourth person in 3 days. What does the fourth person get?

3. Rahul and Ravi undertook to do a piece of work for Rs. 9000. Rahul alone could do the work in the 16 days and Ravi in 24 Days. With the assistance Kamlesh, they finished the work in 8 days. How much money should be given to Kamlesh?

4.  A, B and C can do a piece of work in 24, 30 and 40 days respectively. They began the work together but C left 4 days before completion of the work. In how many days was the work done?

5.  A mason can build a tank in 12 h. After working for 6 h, he took the help of a boy and finished the work in another 5 h. The time that the boys will take alone to complete the work is

6. 96 men can complete a work in 40 days. They all worked for 10 days. But to finish the work before time, contractor brought N more men to work. Because of this, the work got finished in a total of 34 days. What is the value of N?

7. Pipes A and B can fill a tank in 5 hours and 20 hours respectively. If both pipes are opened then, how much time (in hours) it will take to fill the tank?

8. 18 men can complete a project in 30 days and 16 women can complete the same project in 36 days. 15 men start working and after 9 days they are replaced by 18 women. In how many days will 18 women complete the remaining work ?

9. A can do in one day three time the work done by B in one day. They together finish $\frac{2}{5}$ of the work in 9 days. The number of days by which B can do the work alone is :

10. A cistern that would normally be filled in 6 hours is now taking 4 hours more because of a leak. In how much time, will the leak empty the cistern?