 A can finish a piece of work in 5 days. B can do it in 10 days. They work together for two days and then A goes away. In how many days will B finish the work?

Asked on by | Votes 0 | Views: 94 | Tags: quantitative aptitude     | time and work     | Add Bounty

 A can finish a piece of work in 5 days. B can do it in 10 days. They work together for two days and then A goes away. In how many days will B finish the work?

A). 4 days

B). 5 days

C). 6 days

D). 8 days


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

0 vote
Answered by on | Votes 0 |

4 days



2/5 + (2 + x)/10 = 1 => x = 4 days

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (2+5)
Submit:

Other Questions

1.  Prakash alone can complete a job in 12 hours, Jayant alone can complete the same job in 6 hours. How many hours will they take together to complete the job?

2.  36 workers can reap a field in 6 days. If the work is to be completed in 4 days, the extra workers required are

3. A swimming pool has 3 pipes to drain off the water. The first two pipes A and B, operating simultaneously, can empty the pool in 9/16 the time than that taken by C alone. Pipe A, working alone, takes one third the time taken by pipe B. All of them together take 2 hrs 24 minutes to empty the pool. Time taken by pipe A to empty the pool in hours is

4. P is twice as efficient as Q. Q takes 12 days to complete a job. If both of them work together, how much time will they take to complete the job?

5. A work can be completed by 28 women in 36 days. If 4 women leave after working for 18 days, then how many days will be needed to complete the remaining work?

6. Varun alone can do a piece of work in 16 hours while Akash alone can do it in 18 hour. They together took Rs. 576 to do the same work. If with the help of Arun, they finish the piece of work in 5 hour, then how much money is paid to Arun?

7. A can do a work in 20 days and B in 10 days. If they work on it together for 5 days, then what fraction of work is left.

8. 4 men can build a small house in 12 days. How long would it take for 6 men to build the same house?

9.  3 men, 4 women and 6 children can complete a work in 7 days. A woman does double the work a man does and a child does half the work a man does. How many women alone can complete this work in 7 days?

10. A can do a certain work in 12 days. B is 60% more efficient than A. How many days will B and A together take to do the same job ?