 X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16 days. How long will they together take to complete the work?

Asked on by | Votes 0 | Views: 99 | Tags: quantitative aptitude     | time and work     | Add Bounty

 X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16 days. How long will they together take to complete the work?

A). 12 days

B). 13 1/3 days

C). 18 days

D). 21 1/3 days


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

0 vote
Answered by on | Votes 0 |

13 1/3 days




A’s 8 day’s work = 1/40 × 8 = 1/5 

Remaining work = 4/5 

4/5 of the work is finished by Y in 16 days’ 

So, Y can finish the whole work alone in 16 ×5/4 days = 20days 

They both together can finish it in 40 × 20/60 =13 1/3 days.

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (3+1)
Submit:

Other Questions

1. 7 men can complete a piece of work in 12 days. How many additional men will be required to complete double the work in 8 days ?

2. If 10 men can do a piece of work in 12 days, the time taken by 12 men to do the same piece of work will be

3. Amar is 2 times as good a workman as Badal and therefore is able to finish a job in 15 days less than Badal. In how many days can they together complete the job?

4.  A group of workers was put on a job. From the second day onwards, one worker was withdrawn each day. The job was finished when the last worker was withdrawn. Had no worker been withdrawn at any stage,

5.  A and B can do a work in 8 days. B and C can do the same work in 12 days. A , B and C together will do this work in -

6. X can complete 5/7 part of a work in 10 days and Y can complete 3/4 part of the same work in 9 days. In how many days will both complete 13/21 part of the total work

7.  A and B together can do a work in 6 days. If A alone can do the work in 10 days then in how many days can B alone do it ?

8.  A can do a bit of work in 10 days and B can do it in 20 days. They begin the work together . Be that as it may, following 5 days, A leaves off. B will do the remaining work in

9. Pipe A can fill a tank in 4 hours and pipe B can fill the same tank in 3 hours. Pipe C can empty the same full tank in 2 hours. If all the pipes are openedtogether, then what portion of the tank will be filled after 6 hours?

10. Two pipes A and B fill a tank in 4 hours and 6 hours respectively while pipe C empties the tank in 8 hours. If all the pipes A, B and C are started together simultaneously then in how much time will the tank be full?