 A can do a piece of work in 20 days and B can do the same piece of work in 30 days. Find in how many days both can do the work?

Asked on by | Votes 0 | Views: 17 | Tags: quantitative aptitude     | time and work     | Add Bounty

 A can do a piece of work in 20 days and B can do the same piece of work in 30 days. Find in how many days both can do the work?

A). 28

B). 20

C). 34

D). 12


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

0 vote
Answered by on | Votes 0 |

12



NA

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (3+4)
Submit:

Other Questions

1. Mandar works 3 times as fast as Samarth. If Samarth can complete a job alone in 28 days, then in how many days can they together finish the job?

2.  A can do a piece of work in 10 days and B can do it in 15 days and C can do it 20 days. They started the work together and A leaves after 2 days and B leaves after 4 days from the beginning. How long

3. Three pipes A, B and C can fill an empty tank in 30 minutes, 20 minutes and 10 minutes respectively. When the tank is empty, all the three pipes are opened. A, B and C discharge chemical solutions P, Q and R respectively. What is the proportion of the solution R in the liquid in the tank after 3 minutes?

4.  Two persons A and B can finish a piece of work in 60 days, while A, B, and C can finish the same work in 40 days. How many days will C alone take to finish the work ?

5. A takes 10 days less than the time taken by B to finish a piece of work. If both A and B can do it in 12 days, then the time taken by B alone to finish the work is

6. P and Q undertook to do a work for Rs. 7200. P alone could do it in 20 days and Q alone in 12 days. With the assistance of R they finished the work in 5 days. What is the share (in Rs) of R?

7.  Six men or tern boys can do a piece of work in fifteen days. How long would it take for 12 men and 5 boys to do the same piece of work?

8. 3 men or 7 women can do a piece of work in 32 days. The number of days required by 7 men and 5 women to do a piece of work twice as large is

9. P and Q can do a project in 60 and 30 days respectively. In how many days can they complete 90% of the project if they work together?

10. In each of the following questions a question is asked followed by three statements.You have to study the questions and all the given three statements and all the statements and decide whether any information provided in the statement are redundant and can be dispensed with while answering the questions ?