 If A, B and C together can finish a piece of work in 4 days. A alone in 12 days and B in 18 days, then C alone can do it in?

Asked on by | Votes 0 | Views: 19 | Tags: quantitative aptitude     | time and work     | Add Bounty

 If A, B and C together can finish a piece of work in 4 days. A alone in 12 days and B in 18 days, then C alone can do it in?

A). 21 days

B). 15 days

C). 12 days

D). 9 days


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

0 vote
Answered by on | Votes 0 |

9 days



C = 1/4 - 1/12 – 1/18 = 1/9 => 9 days

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (3+3)
Submit:

Other Questions

1.  Two pipes X and Y can separately fill a cistern in 18 and 24 hours respectively. If they are turned on alternately for one hour each, how long will it take to fill the cistern?

2.  A is thrice good a workman as B and therefore is able to finish a job in 60 days less than B. Working together they can do it in?

3. A and B can do a work in 8 days, B and C can do the same work in 12 days. A, B and C together can finish it in 6 days. A and C together will do it in :

4. 2 men and 3 women together or 4 men together can complete a piece of work in 20 days.3 men and 3 women will complete the same work in :

5. Having the same capacity 6 taps fill up a water tank in 36 min. How many taps of the same capacity required to fill up the same water tank in 8 min?

6. A cistern can be filled by two pipes in 10 and 12 min respectively. Both the pipes are opened together for a certain time but, due to defects, only 1/6th of full quantity of water flows through the former and 2/5th of the latter. The defects are detected and rectified. The cistern is filled in 3 min from that moment. How long was it before the detects were rectified?

7. If 3 men or 6 women can do a piece of work in 16 days, in how many days can 12 men and 8 women do the same piece of work?

8. Given below are two quantities named A and B. Based on the given information, you have to determine the relation between the two quantities. You should use the given data and your knowledge of Mathematics to choose between the possible answers. Quantity A: A and B can do a work in 8/3 days, B and C can do the same work in 3 days and A and C can do the same work in 24/5 days. In what time C alone can complete the work? Quantity B: 15

9. A work could be completed in 100 days by some workers. However, due to the absence of 10 workers, it was completed in 110 days.The original number of workers was :

10. can finish a work in 18 days and B in 36 days. If they work on it together for 9 days, then what percent of work is left?