A and B can do a piece of work in 12 days and 24days. Both starts the work together for some time, but B leaves the job 6 days before the work is completed. Find the time in which work is finished.
A and B can do a piece of work in 12 days and 24days. Both starts the work together for some time, but B leaves the job 6 days before the work is completed. Find the time in which work is finished.
A). 10 days
B). 12 days
C). 14 days
D).
5 days
1 answers
Answered by
Guest on
2021-07-09 14:26:37 | Votes
1 |
#
12 days
A & B completes the work in 12*24/12+24 = 12*24/36 = 8 days 2 days work = 2+1/8 = ¼ work Remaining work = 1-1/4 = ¾ A completes ¾ work in ¾*16 = 12 days
Join Telegram Group
Other Questions
1. A and B together can do a work in 16 days, which B and C together can do in 32 days. After A has been working at it for 15 days and B for 13 days, C finished it in 10 days. In how many days A and C alone will do the work respectively?
2. A does $\frac{7}{10}$ part of work in 15 days. After that he completes the remaining work in 4 days with the help of B. In how many days will A and B together do the same work ?
3. A can do a half of certain work in 70 days and B one third of the same in 35 days. They together will do the whole work in.
4. 39 persons can repair a road in 12 days working 5 hours a day. In how many days will 30 persons working 6 hours a day complete the work ?
5. 30 men can repair a road in 18 days. They are Joined by 6 more workers. Now the road can be repaired in
6. Three men P, Q and R working individually can finish a job in 13, 17 and 19 days respectively. They decided to work together but after 3 days, P left and after another one day, Q also left and the remaining work was completed by R. If they got Rs. 1,00,000 collectively for the entire work, what will be the lowest share?
7. P is twice as efficient as Q. Q takes 12 days to complete a job. If both of them work together, how much time will they take to complete the job?
8. If A and B together can finish a piece of work in 20 days B and C in 10 days and C and A in 12 days, then A, B, C jointly can finish the same work in
9. A, B and C can do a job working alone in 6, 9 and 18 days respectively. They all work together for 1 day, then A and B quit. How many days C working alone will take to complete the remainder of the job?
10. P and Q can do a project in 20 and 12 days respectively. In how many days can they complete 40% of the project if they work together?