 A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was compl

Asked on by | Votes 0 | Views: 16 | Tags: quantitative aptitude     | time and work     | Add Bounty

 A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was compl

A). 8 days

B). 10 days

C). 12 days

D). 15 days


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

0 vote
Answered by on | Votes 0 |

12 days



NA

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (5+4)
Submit:

Other Questions

1.  (x-2) men can do a piece of work in x days and (x+7) men can do 75% of the same work in (x-10)days. Then in how many days can (x+10) men finish the work?

2. Namrata gets Rs. 50 if she works for 6 days a week, Rs. 70 if she works for 7 days a week and no money if she works for less than 6 days a week. She received Rs. 260 at the end of the month. Find out the number of weeks for which she worked for 6 days a week.

3. A alone can complete a work in 25 days while B can complete the same work in 20 days. They worked together for 5 days and then A left. In how many days the remaining work will be completed?

4. C is 20% more efficient than A. A and B together can finish a piece of work in 16 days. B and C together can do it in 15 days. In how many days A alone can finish the same piece of work ?

5. While working together on a task, Amit and Sumit received Rs. 600 and Rs. 400 respectively. If Amit can do the task alone in 12 days, then how much time will Sumit take to do the task alone?

6.  Babu and Asha can do a job together in 7 days, Asha is 1 3/4 times are efficient as Babu. The smae job can be done by Asha alone in

7. 8 children and 12 men complete a certain piece of work in 9 days. Each child takes twice the time taken by a man to flnish the work. In how many days will 12 men finish the same work ?

8.  A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?

9. Two pipes P and Q can fill an empty tank in 40 min and 20 min respectively. R can empty a full tank in 30 minutes. If all three are opened together, how much time will they take to empty/fill the tank?

10. A large pool can be filled by two pipes P and Q in 60 and 40 minutes respectively. How many minutes will it take to fill the pool from empty state if Q is used for half the time and P and Q fill it together for the other half?