 A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?

Asked on by | Votes 0 | Views: 75 | Tags: quantitative aptitude     | time and work     | Add Bounty

 A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?

A). 45/2 days

B). 55 days

C). 65/2 days

D). 75/2 days


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

0 vote
Answered by on | Votes 0 |

75/2 days



Whole work is done by A in ( 20 x 5/4 ) = 25 days.

Now, ( 1 - 4/5 ) i.e., 1/5 work is done by A and B in 3 days.

Whole work will be done by A and B in (3 x 5) = 15 days
.
A's 1 day's work = 1/25 , (A + B)'s 1 day's work = 1/15
.
Therefore B's 1 day's work = ( 1/15 - 1/25 ) = 4/150 = 2/75
.
So, B alone would do the work in 75/2 days.

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (2+1)
Submit:

Other Questions

1.  A and B can do a job together in 7 days. A is 13/4 times as efficient as B. The same job can be done by A alone in

2. A garrison of 160 men has provision for 40 days. At the end of 10 days, 40 more men joined them. How many days could the soldiers sustain themselves if they had joined on the first day itself?

3. The ratio of efficiencies of Gary, Sunny and Allan is 3 : 2 : 7. Gary and Sunny work for a week. After that, Sunny leaves and Allan joins Gary. After one more week, the work gets finished. In how many days can Sunny finish the work if he works alone?

4.  25 men can do a piece of work in 24 days. How many men would be required to do the same work in 10 days ?

5.  Shilpa can complete a piece of work in 15 days and Shamita can complete the same piece of work in 24 days. In approximately, how many days can Shilpa and Shamita together complete the same piece of wo

6. A and B working together, can do a piece of work in $4\frac{1}{2}$ hours, B and C working together can do it in 3 hours, C and A working together can do it in $2\frac{1}{4}$ hours. All of them begin the work at the same time. find how much time they will take to finish the piece of work.

7. A and B together can complete a piece of work in 10 2/7days white B and C together can complete the same work in 13 1/3 days. B is 25% more efficient than C. In how many days will A and C together complete the same work ?

8. Raman can do a work in 5 days, Jatin can do the same work in 7 days and Sachin can do the same work in 9 days. If they do the same work together and they are paid Rs. 2860, then what is the share of Raman?

9. A can do 1/3rd of a work in 5 days and B can do 2/5th of this work in 10 days. Both A and B, together can do the work in

10.  A and B can together finish a work in 30 days. They worked together for 20 days and then B left. After another 20 days, A finished he remaining work. In how many days A alone can finish the job?