A, B and C can do a work separately in 16, 32 and 48 days respectively. They started the work together but B left off 8 days and C six days before the completion of the work. In what time is the work finished ?

Asked on by | Votes 0 | Views: 575 | Tags: time and work     | quantitative aptitude     | ssc cgl tier 2 2015     | Add Bounty

A, B and C can do a work separately in 16, 32 and 48 days respectively. They started the work together but B left off 8 days and C six days before the completion of the work. In what time is the work finished ?
1). 10 days
2). 9 days
3). 12 days
4). 14 days


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

3 vote
Answered by on | Votes 3 |
I have read it somewhere 12 days is correct

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (3+1)
Submit:

Other Questions

1. A contractor undertook a contract for a construction work to be completed in 180 days. He engaged 120 labours. But only 1/6th of the work was done in 1/5th of the scheduled time. The additional number of labours that will be required to complete the work in time, is

2. P, Q and R undertook a work for Rs. 55000. Together P and Q complete (8/11)th part of the work. What is the share (in Rs) of R?

3.  A Contractor employed a certain number of workers to finish constructing a road in a certain scheduled time. Sometime later, when a part of work had been completed, he realised that the work would ge

4. A can do a piece of work in 20 days and B can do the same piece of work in 30 days. Find in how many days both can do the work ?

5. If Vinit can do \(\frac{1}{4}\)th of a work in 3 days and Viraj can do \(\frac{1}{6}\)th of the same work in 4 days, how much will Viraj get if both work together and are paid Rs. 360 in all?

6. Two taps can fill a tank in 20 minutes and 30 minutes respectively. There is an outlet tap at exactly half level of that rectangular tank which can pump out 248 liters of water per minute. If the outlet tap is open, then it takes 24 minutes to fill an empty tank. What is the volume of the tank?

7. Pannalal has done 1/3rd of a job in 20 days, Sai Prasad completes the rest of the job in 10 days. In how many days can they together do the job?

8.  A, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work complete

9. A and B can complete a piece of work in 8 days, B and C can do it in 12 days, C and A can do it in 8 days. A, B and C together can complete it in

10.  A and B can do a job in 10 days. B and C can do the same job in 15 days. If all three worked together complete the work in 6 days, then in how many days can B complete the whole job?