A and B can do a plece of work in 28 and 35 days respectively. They began to work together but A leave after sometime and B completed remaining work in 17 days. After how many days did A leave ?
A and B can do a plece of work in 28 and 35 days respectively. They began to work together but A leave after sometime and B completed remaining work in 17 days. After how many days did A leave ? 1). $14\frac{2}{5}$ days 2). 9 days 3). 8 days 4). $7\frac{5}{9}$ days