A contractor was engaged to construct a road in 16 days. After working for 12 days with 20 labours it was found that only $\frac{5}{8}$ th of the road had been constructed. To complete the work in stipulated time the number of extra labours required is :

Asked on by | Votes 0 | Views: 116 | Tags: time and work     | quantitative aptitude     | ssc chsl 2015     | Add Bounty

A contractor was engaged to construct a road in 16 days. After working for 12 days with 20 labours it was found that only $\frac{5}{8}$ th of the road had been constructed. To complete the work in stipulated time the number of extra labours required is :
1). 18
2). 10
3). 12
4). 16


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

2 vote
Answered by on | Votes 2 |
right answer is 16

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (2+2)
Submit:

Other Questions

1. A does half as much work as B in three fourth of the time. lf together they take 18 days to complete the work, how much time will B alone take to do it ?

2. Two pipes, A and B can fill a tank in 16 and 20 hours respectively. If both are opened together and at the end of 4 hours pipe A is closed, How long will the pipe B take to fill the remaining part of the tank?

3. The rate of working of A and B are in the ratio of 2:3. The number of days taken by them to finish the work is in the ratio:

4. A is twice as good a workman as B and B is twice as good a work-man as C. If A and B can together finish a piece of work in 4 days, then C can do it by himself in

5.  A can do a piece of work in 4 days. B can do it in 5 days. With the assistance of C they completed the work in 2 days. Find in how many days can C alone do it?

6.  A, B and C can complete a piece of work in 24, 6 and 12 days respectively. Working together, they will complete the same work in

7.  A, B and C can complete a work separately in 24, 36 and 48 days respectively. They started together but C left after 4 days of start and A left 3 days before the completion of the work. In how many d

8. A alone can complete a work in 15 days and B alone in 20 days. Starting with A, they work on alternate days. The total work will be completed in

9.  Some persons can do a piece of work in 12 days. Two times the number of these people will do half of that work in?

10.  A contractor decided to build a bridge in 35 days. He employed 60 men in the beginning and 40 more after 17 days and completed the work on time. If he had not employed the additional men, how many day