A can do a work in 9 days, if B is 50 % more efficient than A, then in how many days can B do the same work ?

Asked on by | Votes 31 | Views: 1283 | Tags: time and work     | quantitative aptitude     | ssc chsl 2011     | Add Bounty

A can do a work in 9 days, if B is 50 % more efficient than A, then in how many days can B do the same work ?
1). 13.5 days
2). 4.5 days
3). 6 days
4). 3 days


Share on Facebook      Share on Whatsapp       Share on Twitter




2 answers

29 vote
Answered by on | Votes 29 |
Hello, 6 days is correct

Join Telegram Group




26 vote
Answered by on | Votes 26 |

Let total work to be done=1

Then, A's one day work= (total work) / (total days taken by A)

(=1/9)B's one day work= 150% of A's one day work (because B is 50% more efficient)

=(1/9)*(150/100)

=1/6 Total time taken by B to do total work = 6 days

Accepted Answer




Other Questions

1. A particular job can be completed by a team of 10 men in 12 days. The same Job can be completed by a team of 10 women in 6 days. How many days are needed to complete the Job if the two teams work together?

2. Two pipes A and B can fill a tank in 36 hours and 45 hours respectively. If both the pipes are opened simultaneously, how much time will be taken to fill the tank?

3. In a house, there are six 40 W lamps which are switched on for 5 hours a day and three 80 W fans which are switched on for 10 hours a day. If electricity costs Rs.2 per kilowatt hours. What is the monthly electricity bill?

4. If 8 men or 12 women can do a piece of work in 25 days, in how many days can the same work be done by 6 men and 11 women?

5. A takes 12 days less than the time taken by B to finish a piece of work. If both A and B can do it in 8 days, then the time taken by B alone to finish the work is

6. A, B and C can complete a work in 10, 12 and 15 days respectively. All three of them starts together but after 2 days A leaves the job and B left the job 3 days before the work was completed. C completed the remaining work alone. In how many days was the total work completed?

7. A and B together can complete a piece of work in 72 days, B and C together can complete it in 120 days, and A and C together in 90 days. In what time can A alone complete the work ?

8. A can do a piece of work in 18 days.He worked at it for 12 days and B finished the remaining work in 8 days. B alone can do the whole work in

9.  X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him till the completion of the work. How long did the work last?

10. Amar started doing a work, but left it after 6 days. Chetan completed the remaining work in 8 days. If Chetan alone can do the work in 24 days, how many days would Amar take to complete the remaining work?