Working 8 hours a day. Anu can copy a book in 18 days. How many hours a day should she work so as to finish the work in 12 days ?

Asked on by | Votes 0 | Views: 45 | Tags: time and work     | quantitative aptitude     | ssc constable gd 2011     | Add Bounty

Working 8 hours a day. Anu can copy a book in 18 days. How many hours a day should she work so as to finish the work in 12 days ?
1). 12 hours
2). 10 hours
3). 11 hours
4). 13 hours


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

2 vote
Answered by on | Votes 2 |
option 1 is the right answer

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (1+4)
Submit:

Other Questions

1. A alone can complete a work in 25 days while B can complete the same work in 20 days. They worked together for 5 days and then A left. In how many days the remaining work will be completed?

2. A and B can do a piece of work in 72 days, B and C can do it in 120 days, A and C can do it in 90 days. In how many days all the three together can do the work ?

3.  If 12 men or 20 women can do a piece of work in 54 days, then in how many days can 9 men and 12 women together do the work?

4. Given below are two quantities named A & B. Based on the given information, you have to determine the relation between the two quantities. You should use the given data and your knowledge of Mathematics to choose between the possible answers. Quantity A: A and B together, B and C together and C

5. Two pipes P and Q can fill the tank alone in 60 and 90 hours respectively. If they are opened together, then in how many hours will the tank be filled?

6. Each of the questions consists of a question followed by three statements. You have to study the question followed by three statements and decide which of the statements is/are necessary to answer the questions.

7.  A and B can do a work in 18 day, B and C in 30 days, A and C in 22 (1/2) days. In how many days can A,B and C individually do the work?

8. M can complete 3/4 part of a work in 12 days and N can complete 2/7 part of the same work in 8 days. In how many days will both complete 11/14 part of the total work?

9.  A can do a piece of work in 21 days and B in 28 days. Together they started the work and B left after 4 days. In how many days can A alone do the remaining work?

10. A, B and C individually can do a work in 10 days, 12 days and 15 days respectively. If they start working together, then the number of days required to finish the work is