18 boys can do a piece of work in 24 days. In how many days can 27 boys do the same work ?

Asked on by | Votes 0 | Views: 86 | Tags: time and work     | quantitative aptitude     | ssc chsl 2012     | Add Bounty

18 boys can do a piece of work in 24 days. In how many days can 27 boys do the same work ?
1). 16 days
2). 32 days
3). 23 days
4). 48 days


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

1 vote
Answered by on | Votes 1 |
is 16 days is the correct answer?? am i right?

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (3+4)
Submit:

Other Questions

1.  What is the total number of units manufactured by Company C over all the years together ?

2.  A tank is normally filled in 12 hrs but takes four hrs longer to fill because of a leak in its bottom.

3.  Rajesh and Ajay can complete a job in 16 days. Rajesh alone can do it in 24 days. How long will Ajay alone take to finish the whole work?

4. A builder decided to build a farm house in 40 days. He employed 100 workers in the beginning and 100 more after 35 days and completed the construction in stipulated time. If he had not employed the additional workers, how many days behind schedule would it have been finished?

5. A can do a work in 15 days and B in 20 days. If they work on it together for 5 days, then what fraction of work is left?

6. P can complete a work in 15 days and Q in 24 days. They began the work together but Q left the work 2 days before its completion. In how many days was the work completed?

7. A is 30% more efficient than B, and can alone do a work in 23 days. The number of days, in which A and B, working together can finish the Job is

8. A man is twice as fast as a woman and a woman is twice as fast as a boy. If all of them i.e. a man, a woman and a boy can finish a work together in 4 days, in how many days a boy shall do it alone?

9. Two pipes, A and B can fill a tank in 16 and 20 hours respectively. If both are opened together and at the end of 4 hours pipe A is closed, How long will the pipe B take to fill the remaining part of the tank?

10. Two pipes X and Y can fill the cistern in 49 ½ minutes and 27 minutes respectively. Both pipes are opened. The cistern will be filled in 22 minutes, if pipe Y is closed after: