Makarand works 2 times as fast as Samarjit. If Samarjit can complete a job alone in 27 days, then in how many days can they together finish the job?

Asked on by | Votes 6 | Views: 55 | Tags: ssc     | ssc chsl     | ssc chsl tier 1     | ssc chsl 2017     | ssc chsl 29 01 2017     | time and work     | quantitative aptitude     | Add Bounty

Makarand works 2 times as fast as Samarjit. If Samarjit can complete a job alone in 27 days, then in how many days can they together finish the job?
1). 7days
2). 9days
3). 2days
4). 1days

SSC CGL Books


Share on Facebook      Share on Whatsapp       Share on Twitter




2 answers

3 vote
Answered by on | Votes 3 |
This question was asked some where in previous year papers of ssc, and correct answer was option 2

Join Telegram Group




1 vote
Answered by on | Votes 1 |

9 days

Accepted Answer




Other Questions

1. A water filling Pipe P is 5 times faster than second Pipe Q. If P fills a cistern in 30 minutes. How long will it take to fill the tank, when both the pipes are kept in operation simultaneous?

2. Each of these questions have a question followed by information given in three statements I, II and III. You have to study the question along with the information in three statements and decide that the information in which of the statement(s) is/are necessary to answer the question ?

3. If A and B can together earn Rs. 540 in 6 days, B and C can together earn Rs. 420 in 5 days and A and C can together earn Rs. 644 in 7 days then in how many days can A, B and C working together earns Rs. 532?

4.  A man can do a job in 15 days. His father takes 20 days and his son finishes it in 25 days. How long will they take to complete the job if they all work together?

5. Working 5 hours a day, A can complete a work in 8 days and working 6 hours a day, B can complete the same work in 10 days. Working 8 hours a day, they can jointly complete the work in

6. X can complete 5/7 part of a work in 10 days and Y can complete 3/4 part of the same work in 9 days. In how many days will both complete 13/21 part of the total work

7. Anil and Sujay can do a work in 16 days. Anil is 4/3 times efficient than Sujay. How many days will Anil take to finish the work alone?

8. A can do $\frac{1}{6}$ of a work in 5 days and B can do $\frac{2}{5}$ of the work in 8 days, in how many days, can both A and B together do the work ?

9. A and B together can complete a particular task in 4 days. If A alone can complete the same task in 12 days, how many days will B take to complete the task if he works alone ?

10.  10 women can complete a work in 8 days and 10 children take 12 days to complete the work. How many days will 6 women and 3 children together take to complete the work?