A work can be finished In 14 days by 36 workers. If the work were to be finished in 8 days, how many additional workers would be required ?

Asked on by | Votes 0 | Views: 64 | Tags: sbi     | sbi clerk     | sbi clerk 27 july 2014     | time and work     | quantitative aptitude     | Add Bounty



A work can be finished In 14 days by 36 workers. If the work were to be finished in 8 days, how many additional workers would be required ?
1). 29
2). 33
3). 23
4). 31


Share on Facebook      Share on Whatsapp       Share on Twitter




2 answers

0 vote
Answered by on | Votes 0 |
Solution

Using the formula, $M_1 D_1 = M_2 D_2$

=> $36 \times 14 = M_2 \times 8$

=> $M_2 = \frac{36 \times 14}{8} = 63$

$\therefore$ Additional workers = 63 - 36 = 27

Join Telegram Group




1 vote
Answered by on | Votes 1 |
Solution

Using the formula, $M_1 D_1 = M_2 D_2$

=> $36 \times 14 = M_2 \times 8$

=> $M_2 = \frac{36 \times 14}{8} = 63$

$\therefore$ Additional workers = 63 - 36 = 27




Answer This Question

Name:
Email:
Answer :
Sum of (2+3)
Submit:

Other Questions

1. 14 men can do a work in 18 days, 15 women can do a work in 24 days. If 14 men work for first three days and 10 women work after that for three days, find the part of work left after that?

2. X can do a piece of work in 'p' days and Y can do the same work in 'q' days . Then the number of days in which X and Y can together do that work is

3. Working 9 hours a day, Manish can read a book in 16 days. How many hours a day should he work so as to finish the same work in 24 days?

4. Given below are two quantities named A and B. Based on the given information, you have to determine the relation between the two quantities. You should use the given data and your knowledge of Mathematics to choose between the possible answers. Quantity A: A boy can do a homework in 2 hours. The nu

5.  A certain number of men can do a work in 54days. If there were 6 men more it could be finished in 6 days less. How many men were there in the beginning?

6.  Xavier can do a job in 40 days. He worked on it for 5 days and then Paes finished it in 21 days. In how many days Xavier and Paes can finish the work?

7. To do a certain work, B would take time thrice as long as A and C together and C twice as long as A and B together. The three men together complete the work in 10 days. The time taken by A to complete the work separately is

8.  15 labourers complete a work in 10 days working 6 hours per day. If 18 labourers are employed on that work and the work is to be completed in 5 days then how many hours per day the work should be cont

9. Three men, four women and six children can complete a work in 7 days. A women does double the work a man does and a child does half the work a man does. How many women alone can complete this work in 7 days ?

10.  9 men working 7 hours a day can complete a piece of work in 15 days. How many days can 6 men working for 9 hours a day, complete the same piece of work?