Time and work Practice Questions & Answers

0 vote

 P alone can complete a piece of work in 6 days. Work done by Q alone in one day is equal to one-third of the work done by P alone in one day. In how many days can the work be completed if P and Q work

Asked on by Guest | Votes 0

 P alone can complete a piece of work in 6 days. Work done by Q alone in one day is equal to one-third of the work done by P alone in one day. In how many days can the work be completed if P and Q work

A). 4(3/4)

B). 4(1/2)

C). 4

D). 5

0 vote

 A, B and C can do a work in 90, 30 and 45 days respectively. If they work together, in how many days will they complete the work?

Asked on by Guest | Votes 0

 A, B and C can do a work in 90, 30 and 45 days respectively. If they work together, in how many days will they complete the work?

A). 15

B). 10

C). 20

D). 25

0 vote

 A can do a work in 9 days and B can do the same work in 18 days. If they work together, in how many days will they complete the work?

Asked on by Guest | Votes 0

 A can do a work in 9 days and B can do the same work in 18 days. If they work together, in how many days will they complete the work?

A). 8

B). 7

C). 6

D).  5

0 vote

 A and B can do a work in 4 hours and 12 hours respectively. A starts the work at 6AM and they work alternately for one hour each. When will the work be completed?

Asked on by Guest | Votes 0

 A and B can do a work in 4 hours and 12 hours respectively. A starts the work at 6AM and they work alternately for one hour each. When will the work be completed?

A). 4 days

B). 7 days

C). 5 days

D). 6 days

0 vote

 30 men can do a work in 40 days. When should 20 men leave the work so that the entire work is completed in 40 days after they leave the work?

Asked on by Guest | Votes 0

 30 men can do a work in 40 days. When should 20 men leave the work so that the entire work is completed in 40 days after they leave the work?

A). 5 days

B). 10 days

C). 15 days

D). 20 days