Time and work Practice Questions & Answers

0 vote

 9 men working 7 hours a day can finish a bit of work in 15 days. In how long can 6 men functioning for 9 hours a day, complete the same bit of work?

Asked on by Guest | Votes 0

 9 men working 7 hours a day can finish a bit of work in 15 days. In how long can 6 men functioning for 9 hours a day, complete the same bit of work?

A). 63/4 days

B). 16 days

C). 67/4 days

D).  35/2 days

0 vote

 A does half as much work as B in three ?fourth of the time. On the off chance that together they take 18 days to finish the work, the amount of time might B takes to do it?

Asked on by Guest | Votes 0

 A does half as much work as B in three ?fourth of the time. On the off chance that together they take 18 days to finish the work, the amount of time might B takes to do it?

A). 30 days

B). 35 days

C). 40 days

D). none of these

1 vote

 A can do a bit of work in 10 days and B can do it in 20 days. They begin the work together . Be that as it may, following 5 days, A leaves off. B will do the remaining work in

Asked on by Guest | Votes 1

 A can do a bit of work in 10 days and B can do it in 20 days. They begin the work together . Be that as it may, following 5 days, A leaves off. B will do the remaining work in

A). 5 days

B). 6 days

C). 8 days

D). 10 days

0 vote

 A can do a bit of work in 24 days while B alone can do it in 16 days. With the help of C, they can complete the work in 8 days. C alone can take every necessary step in

Asked on by Guest | Votes 0

 A can do a bit of work in 24 days while B alone can do it in 16 days. With the help of C, they can complete the work in 8 days. C alone can take every necessary step in

A).  32 days

B).  36 days

C).  40 days

D).  48 days

0 vote

 A and B together can finish a bit of work in 12 days, B and C can do it in 20 days and C and A do it 15 days. A, B and C together can finish it in

Asked on by Guest | Votes 0

 A and B together can finish a bit of work in 12 days, B and C can do it in 20 days and C and A do it 15 days. A, B and C together can finish it in

A). 6 days

B). 9 days

C). 10 days

D). 21/2 days