ExamCompetition Forum Question Papers Ask A Question Mock Test Learn & Earn Sign Up Login Menu



32 vote

A, B and C. each working alone, can finish a piece of work in 27, 33 and 45 days respectively. A starts by working alone for 12 days, then B takes over from A and works for 11 days. At this stage C takes over from B and completes the remaining work. In how many days the whole work was completed ?

Asked on by | Votes 32 | Views: 2228 | Tags: sbi     | sbi clerk     | sbi clerk 29 may 2016     | time and work     | quantitative aptitude     | Add Bounty



A, B and C. each working alone, can finish a piece of work in 27, 33 and 45 days respectively. A starts by working alone for 12 days, then B takes over from A and works for 11 days. At this stage C takes over from B and completes the remaining work. In how many days the whole work was completed ?
1). 33
2). 31
3). 39
4). 35


Share on Facebook      Share on Whatsapp       Share on Twitter




2 answers

32 vote
Answered by on | Votes 32 |
Solution

A's 1 day's work = $\frac{1}{27}$

=> A's 12 days work = $\frac{1}{27} \times 12 = \frac{4}{9}$

Remaining work = $1 - \frac{4}{9} = \frac{5}{9}$

Similarly, B's 11 days work = $\frac{1}{33} \times 11 = \frac{1}{3}$

Remaining work = $\frac{5}{9} - \frac{1}{3} = \frac{2}{9}$

Now, days taken by C to complete the work = 45 days

=> Days taken to complete $\frac{2}{9}$ th of the work = $\frac{2}{9} \times 45 = 10$ days

$\therefore$ Days in which the whole work is completed = 12 + 11 + 10 = 33 days

Accepted Answer

Join Telegram Group




28 vote
Answered by on | Votes 28 |
Solution

A's 1 day's work = $\frac{1}{27}$

=> A's 12 days work = $\frac{1}{27} \times 12 = \frac{4}{9}$

Remaining work = $1 - \frac{4}{9} = \frac{5}{9}$

Similarly, B's 11 days work = $\frac{1}{33} \times 11 = \frac{1}{3}$

Remaining work = $\frac{5}{9} - \frac{1}{3} = \frac{2}{9}$

Now, days taken by C to complete the work = 45 days

=> Days taken to complete $\frac{2}{9}$ th of the work = $\frac{2}{9} \times 45 = 10$ days

$\therefore$ Days in which the whole work is completed = 12 + 11 + 10 = 33 days




Other Questions

1. Sunil completes a work in 4 days, whereas Dinesh completes the work in 6 days. Ramesh works $1\frac{1}{1}$ times as fast as Sunil. The three together can complete the work in

2. P and Q can complete a task in 50 and 20 days respectively. In how many days can they complete 70% of the task if they work together?

3. A can do a piece of work in 20 days. He worked for 4 days and B finished the remaining work in 28 days. B alone can do the whole work in how many days?

4. If 7 men working 7 hrs a day for each of 7 days produce 7 units of work, then the units of work produced by 5 men working 5 hrs a day for each of 5 days is

5.  A can do a piece of work in 20 days and B can do the same piece of work in 30 days. Find in how many days both can do the work?

6. A can do a work in 12 days and B in 24 days. If they work on it together for 4 days, then what fraction of work is left?

7. A man travelled a distance of 60 km in 7 hours. He travelled partly on foot @ 6 km/hr and partly on bicycle @ 12 km/hr. What is the distance (in kms) travelled on foot?

8. Mandar works 3 times as fast as Samarth. If Samarth can complete a job alone in 28 days, then in how many days can they together finish the job?

9. B is 1.5 times as efficient as A. If A can complete $${6 \over 7}$$th of a given task in 12 days, what fraction of the same task would remain incomplete if B works on it independently for 6 days only?

10. L alone can do a work in 100 hours. M alone can do the same in 150 hours. L, M and N together can do the same work in 30 hours. In how many hours can N alone do the work?