Two pipes 1 and 2 can fill a tank in 2.5 hours and 4 hours respectively. If both pipes are opened together, then after what time should 1 be closed so that the tank is full in 2 hours, from the start

Asked on by | Votes 0 | Views: 129 | Tags: time and work     | quantitative aptitude     | Add Bounty

Two pipes 1 and 2 can fill a tank in 2.5 hours and 4 hours respectively. If both pipes are opened together, then after what time should 1 be closed so that the tank is full in 2 hours, from the start
1). 1 hr. 10 min
2). 1 hr. 15 min
3). 1 hr. 20 min
4). 1 hr. 30 min


Share on Facebook      Share on Whatsapp       Share on Twitter




2 answers

1 vote
Answered by on | Votes 1 |

Given that, two pipes P and Q can fill a tank in 2.5 hours and 4 hours resp.

∴ Efficiency of pipe 1 = 1/2.5 = 2/5 and that of pipe 2 = 1/4

Let x be the time after which pipe 1 should be closed.

According to the question, total work done by both the pipes

⇒ (1/4 × 2) + (2/5 × x) = 1

⇒ 2x/5 = 1/2

⇒ x = 1.25 hours

⇒ Time required = 1 hr 15 min

Join Telegram Group




2 vote
Answered by on | Votes 2 |

Given that, two pipes P and Q can fill a tank in 2.5 hours and 4 hours resp.

∴ Efficiency of pipe 1 = 1/2.5 = 2/5 and that of pipe 2 = 1/4

Let x be the time after which pipe 1 should be closed.

According to the question, total work done by both the pipes

⇒ (1/4 × 2) + (2/5 × x) = 1

⇒ 2x/5 = 1/2

⇒ x = 1.25 hours

⇒ Time required = 1 hr 15 min




Answer This Question

Name:
Email:
Answer :
Sum of (4+5)
Submit:

Other Questions

1.  A is twice efficient as B and together they do the same work in as much time as C and D together. If C and D can complete the work in 20 and 30 daysrespectively, working alone ,then in how many days A

2.  Shilpa can complete a piece of work in 15 days and Shamita can complete the same piece of work in 24 days. In approximately, how many days can Shilpa and Shamita together complete the same piece of wo

3. 45 men can complete a work in 16 days. Four days after they started working. 36 more men joined them. How many days will they now take to complete the re- maining work ?

4.  A cistern can be filled by 3 pipes in 30, 40 and 60 min and emptied by an escape pipe in half an hour the 3 taps are turned on at noon but the escape pipe is at the same time accidentally left open a

5.  Anil can do a work in 15 days while Sunil can do it in 25 days. How long will they take if both work together?

6. Two pipes X and Y can fill an empty tank in 16 hours and 20 hours respectively. Pipe Z alone can empty the completely filled tank in 25 hours. Firstly both pipes X and Y are opened and after 6 hours pipe Z is also opened. What will be the total time (in hours) taken to completely fill the tank?

7.  A and B can together finish a work 30 days. They worked together for 20 days and then B left. After another 20 days, A finished the remaining work. In how many days A alone can finish the work?

8.  A can do a piece of work in 28 days. B is 40% more efficient than A. Find the number of days taken by B to do the same piece of work.

9. A pipe can fill a tank in 14 hours. Due to the leak in its bottom, the tank is filled in 16 hours. If the tank is full, then that leak can empty the tank in how many hours?

10.  A’s 2 days work is equal to B’s 3 days work. If A can complete the work in 8 days then to complete the work B will take: