Given below are two quantities named A & B. Based on the given information, you have to determine the relation between the two quantities. You should use the given data and your knowledge of Mathematics to choose between the possible answers. Quantity A: Three persons P, Q and R working togethe

Asked on by | Votes 0 | Views: 111 | Tags: time and work     | quantitative aptitude     | Add Bounty

Given below are two quantities named A & B. Based on the given information, you have to determine the relation between the two quantities. You should use the given data and your knowledge of Mathematics to choose between the possible answers.

Quantity A: Three persons P, Q and R working together can complete a piece of work in 30 days. P & R together can finish the work in half the time Q can finish it and P & Q together are thrice efficient than R. In how many days Q can finish the work alone?

Quantity B: Two persons A and B can finish a piece of work in 12 days. If A works thrice its efficiency and B works half of its efficiency then the work will be finished in 8 days. Find the time in which A will complete thrice the work alone.
1). Quantity A > Quantity B
2). Quantity A < Quantity B
3). Quantity A ≥ Quantity B
4). Quantity A ≤ Quantity B


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

1 vote
Answered by on | Votes 1 |

Quantity A:

Suppose the efficiencies of P, Q and R is p, q and r respectively

Given that P & R together can finish the work in half the time Q can finish it

⇒ Efficiency of P & R together will be twice the efficiency of Q

⇒ (p + r) ? q = 2 ? 1 = 8 ? 4 (Let)

P & Q together are thrice efficient than R

⇒ (p + q) ? r = 3 ? 1 = 9 ? 3

⇒ p ? q ? r = 5 ? 4 ? 3

Since P, Q and R working together can complete the work in 30 days

⇒ Total units of work = 12 × 30 = 360 units

⇒ Time taken by Q to complete the work = 360/4 = 90 days

Quantity B:

Suppose the efficiencies of A and B are ‘a’ and ‘b’ respectively

According to the given statements :

⇒ 12(a + b) = 8(3a + b/2)

⇒ 12a + 12b = 24a + 4b

⇒ 12a = 8b

⇒ a ? b = 2 ? 3

Since A and B can finish the work in 12 days

⇒ Total units of work = 5× 12 = 60 units

⇒ Time taken by A to complete thrice the work = 3 × 60/2 = 90 days

∴ Quantity A = Quantity B

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (4+2)
Submit:

Other Questions

1. S and T can finish a work in 50 days. They worked together for 20 days and then left. How much of the work is left?

2.  A can do a piece of work in 4 days and B can complete the same work in 12 days. What is the number of days required to do the same work together?

3.  A is thrice as good a workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:

4. A man, a woman and a boy can together complete a piece of work in 3 days. If a man alone can do It in 8 davs and a boy alone in 18 days, how long will a woman alone take to complete the work?

5. X can do a piece of work in 24 days. When he had worked for 4 days, Y Joined him. If complete work was finished in 16 days. Y can alone finish that work in :

6. Running at the same constant rate, 6 identical machines can produce a total of 270 balls per 3 minutes. At this rate, how many balls could 10 such machines produce in 2 minutes?

7.  A can do a piece of work in 1o days, B can do the same work in 15 days. They work for 5 days. The rest of work finished by C in 2 days. If they get Rs 1500 for the whole work, the daily wages of B and

8. P is twice as efficient as Q. Q takes 12 days to complete a job. If both of them work together, how much time will they take to complete the job?

9. Twenty women together can complete a work in 16 days, 16 men together can complete the same work in 15 days. The ratio of the working capacity of a men to that of a women is :

10. Rahim does \(\frac{7}{{10}}\) of a work in 21 hours. He then calls in Bablu and they together finish the remaining work in 6 hours. How long Bablu alone would take to do the whole work?