ExamCompetition Forum Question Papers Ask A Question Mock Test Learn & Earn Sign Up Login Menu



0 vote

Peter can do a piece of work in 20 hours and Quagmire can do it in 5 hours. Peter and Quagmire undertook to do it for $1008. With the help of Goldman, they finished the work together in 2 hours. How much money did Goldman get?

Asked on by | Votes 0 | Views: 92 | Tags: time and work     | quantitative aptitude     | Add Bounty

Peter can do a piece of work in 20 hours and Quagmire can do it in 5 hours. Peter and Quagmire undertook to do it for $1008. With the help of Goldman, they finished the work together in 2 hours. How much money did Goldman get?


1).

$201.6


2). $504
3). $252
4). Data inadequate


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

1 vote
Answered by on | Votes 1 |

Amount of work Peter can do in an hour = (1/20)

Amount of work Quagmire can do in an hour = (1/5)

Let Goldman is able to complete one piece of work in 'n' hours,

⇒ Then the amount of work Goldman does in an hour = 1/n

⇒ Thus, total work done by all 3 in an hour = (1/20) + (1/5) + (1/n)

⇒ Total amount of work done by all 3 in a couple of hours (2 hours) = {(1/20) + (1/5) + (1/n)} × 2       ---- (1)

From given data,

The entire piece of work is completed in 2 hours.

⇒ {(1/20) + (1/5) + (1/n)} × 2 = 1

⇒ {(1/20) + (1/5) + (1/n)} = ½

⇒ (1/n) = ½ – {(1/20) + (1/5)}

⇒ (1/n) = ½ – (5/20)

⇒ (1/n) = ¼

As Goldman does 1/4th of the work in an hour.

⇒ They finished the work in 2 hours

Therefore, part of the work done by Goldman = 2 × ¼ = ½

∴ He gets ½ × 1008 = $504

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (1+4)
Submit:

Other Questions

1. Water flows into a tank which is 200 m long and 150 m wide, through a pipe of cross-section 0.3 m × 0.2 m at 20 km/hour. Then the time (in hours) for the water level in the tank to reach 8 m is

2. A and B can do a Job in 6 and 12 days respectively . They began the work together but A leaves after 3 days. Then the total number of days needed for the completion of the work is :

3. A, B and C are employed to do a piece of work for Ra. 5,290. A and B together are supposed to do $\frac{19}{23}$ of the work and B and C together $\frac{8}{23}$ of the work. Then A should be paid

4. A pipe can fill a tank in 14 hours. Due to the leak in its bottom, the tank is filled in 16 hours. If the tank is full, then that leak can empty the tank in how many hours?

5. Babu and Asha can do a Job together in 7 days. Asha is 1 3/4 times as efficient as Babu. The same Job can be done by Asha alone in

6.  16 men or 20 women can finish a work in 25 days. How many days 28 men and 15 women will take to finish this job?

7.  'A'can do a piece of work in 10 days and'B'can do the same work in 15 days. How long will it take ifboth work together ?

8. Working 5 hours a day, A can complete a piece of work in 8 days and working 6 hours a day B can complete the same work in 10 days. Working 8 hours a day both of them can complete the work in ____.

9. A can do a piece of work in 25 days and B can do the same work in 30 days. They work together for 5 days, how much of work is left ?

10. To complete a job, Abhay alone takes thrice as long as Bittu and Chanakya together. Bittu would take five times as long as Abhay and Chanakya together. All three together complete the work in 10 days. How many days are required by Chanakya to finish the work alone?