22 vote

P is four times as efficient as Q. P can complete a work in 45 days less than Q. If both of them work together, then in how many days the work will be completed?

Asked on by | Votes 22 | Views: 1813 | Tags: time and work     | quantitative aptitude     | Add Bounty

P is four times as efficient as Q. P can complete a work in 45 days less than Q. If both of them work together, then in how many days the work will be completed?
1). 10
2). 12
3). 15
4). 30


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

19 vote
Answered by on | Votes 19 |

Let efficiency of Q be q.

⇒ Efficiency of P = 4q.

Time taken by Q = 1/q

Time taken by P = 1/4q

P can complete a work in 45 days less than Q

⇒ 1/4q = 1/q - 45

-3/4q = -45

q = 3/45 = 1/60

Combined efficiency = q + 4q = 5q.

Time taken by them together = 1/5q = 1/(5 × 1/60) = 12 days.
Accepted Answer

Join Telegram Group




Other Questions

1.  16 boys or 24 girls can construct the wall in 6 days. the number of days that 8 boys and 12 girls Will take to construct?

2. A farmer can plough a field working 6 hours per day in 18 days. The worker has to work how many hours per day to finish the same work in 12 days ?

3. A work can be finished In 14 days by 36 workers. If the work were to be finished in 8 days, how many additional workers would be required ?

4. In a tank of capacity 4200 liters, a total of 7 pipes are attached. Some of them fill the tank at 4 liters per minute while others at 11 liters per minute. It takes a total of 1 hour and 40 minutes to fill the tank if all pipes are opened. How may pipes have a rate of flow of 4 liters per minute?

5. 2 men and 3 boys can do a piece of work in 10 days while 3 men and 2 boys can do the same work in 8 days. In how many days can 2 men and 1 boy do the work ?

6. Manish can complete a work in 21 days and Karan can complete the same work in 28 days. If both together work for 7 days, then what fraction of total work is left?

7.  A, B and C completed a piece of work costing Rs.1800. A worked for 6 days, B for 4 days and C for 9 days. If their daily wages are in the ratio 5 : 6 : 4, how much amount will be received by A?

8.  X men can do a work in 120 days. If there were 20 men less, the work would have taken 60 days more. What is the value of X?

9. 5 men can do a piece of work in 12 days and 10 women can do the same work in 15 days. 5 men and 10 women undertook the same work for Rs. 36,000. They finished the work in 5 days with the help of 15 children. What is the share of 5 children?

10. Two pipes can fill a tank in 10 hours and 12 hours respectively, while a third pipe empties the full tank in 20 hours. If all the three pipes operate simultaneously, in how much time the tank will be filled?