A can do a piece of work in 6 days and B can do it in 4 days separately. How many days would it take for both A and B to finish the same work together?

Asked on by | Votes 0 | Views: 22 | Tags: time and work     | quantitative aptitude     | Add Bounty

A can do a piece of work in 6 days and B can do it in 4 days separately. How many days would it take for both A and B to finish the same work together?
1). 12/7
2). 12/15
3). 24/10
4). 11/5


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

1 vote
Answered by on | Votes 1 |

Given that, A can do a task in 6 days.

∴ 1 day’s work by A = 1/6

Also, B can do it in 4 days

∴ 1 day’s work by B = 1/4

1 day’s work by both A and B together = $(\frac{1}{6}\; + \;\frac{1}{4}\; = \;\frac{{2\; + \;3}}{{12}}\; = \;\frac{5}{{12}})$

To do the whole work, time taken by A and B together = $(\frac{1}{{\frac{5}{{12}}}}\; = \;\frac{{12}}{5}\; = \;\frac{{24}}{{10}})$

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (4+2)
Submit:

Other Questions

1.  8 men can do a piece of work in 12 days. 4 women can do it in 48 days and 10 children can do it in 24 days. In how many days can 10 men, 4 women and 10 children together complete the piece of work?

2. A and B together can do a work in 10 days, B and C together can do the same work in 6 days, A and C together can do the work in 12 days. Then A, B and C together can do the work in

3. If A and B together do a job in 7.5 days and if A could do the job in 10 days if he worked alone. How many days would B take to do the job if he worked alone? 

4. A and B can do a work in 12 days, B and C in 15 days and C and A in 20 days. If A, B and C work together, they will complete the work in :

5.  A, B and C can complete a piece of work in 24,6 and 12 days respectively.Working together, they will complete the same work in:

6.  A certain number of men complete a piece of work in 60 days. If there were 8 men more, the work could be finished in 10 days less. How many men were originally there?

7. A man can do a piece of work in 16 days. With the help of a boy he does the work in 12 days. If they get Rs. 80 for this work, what is the boy’s share?

8. Khaleesi can do a piece of work in 15 days; John Snow can do it in 12 days. They work together for 6 days. The rest of the work was done by Cersi in 4 days. If they get Rs. 2400 for the whole work, the daily wages of john Snow and Cersi are:

9. A and B together can do a work in 8 days, B and C together in 6 days while C and A together in 10 days, if they all work together, the work will be completed in :