 A particular job can be completed by a team of 10 men in 12 days. The same job can be completed by a team of 10 women in 6 days. How many days are needed to completed the job if the two teams work tog

Asked on by | Votes 0 | Views: 80 | Tags: quantitative aptitude     | time and work     | Add Bounty

 A particular job can be completed by a team of 10 men in 12 days. The same job can be completed by a team of 10 women in 6 days. How many days are needed to completed the job if the two teams work tog

A). 1 day

B). 2 days

C). 3 days

D). 4 days


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

0 vote
Answered by on | Votes 0 |

4 days



Consider men’s work days as one group and women’s working days as other group 

Then, the required No. of days = 12 × 6/18 = 4 days.

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (2+4)
Submit:

Other Questions

1. Two labourers A and B are paid a total of Rs 650 per day. If A is paid 160 percent of what is paid to B, how much (in Rs) is B paid?

2. A can do a work in 5 days less than the time taken by B to do it. If both of them together take $11\frac{1}{9}$ days, then the time taken by 'B' alone to do the same work (in days) is

3. A and B together can complete a work in 24 days. B alone does 1/3rd part ofthis work in 12 days. How many days will A alone take to complete the remaining work?

4.  A and B can together finish work in 30 days. They worked at it for 10 days together & then B left. The remaining work was done by A alone in 30 more days. B alone can finish the work in

5.  A can do a certain work in the same time in which B and C together can do it. If A and B together could do it in 10 days and C alone in 50 days, then B alone could do it in:

6. 4 men and 3 women finish a job in 6 days, and 5 men and 7 women can do the same job in 4 days. How long will 1 man and 1 woman take to do the work ?

7.  P can complete work in 12 days working 8 hrs a day. Q can complete the same work in 8 days working10 hrs a day. If both P and Q working 8 hrs a day in how many days can they complete the work?

8. A and B undertook a piece of work for Rs.9000. A alone could do it in 16 days and B alone in 24 days. With the assistance of C they finished the work in 8 days. Then C’s share in the total money is?

9. Amit and sujit together can complete an assignment of data entry in five days. Sujit?s speed 80% of Amit?s speed and the total key depressions in the assignment are 5,76,000. What is Amit?s speed in key depressions per hour if they work for 8 hours a day ?

10. A cistern has two pipes A and B. A can fill it in 16 minutes and B can fill it 20 minutes. If another pipe C can empty it in 40 min, how much time will it take to be filled, if all the pipes opened at the same time?