P can finish a work in 25 days and Q can do the same work in 20 days. Q worked for 8 days and left the job. In how many days, P alone can finish the remaining work?
P can finish a work in 25 days and Q can do the same work in 20 days. Q worked for 8 days and left the job. In how many days, P alone can finish the remaining work?
Answered by Bebita on | Votes 15 | # | Last Updated: 2021-11-14 13:33:36
15 days
0 vote
Answered by Vishal Adhav on | Votes 0 | # | Last Updated: 2022-09-27 07:28:41
15 days
1 vote
Answered by SAPAVAT MOTHILAL on | Votes 1 | # | Last Updated: 2022-09-27 07:27:46
Total work is 100
And P's efficiency is 4 and Q's efficiency is 5, so Q works for only 8 days then his total work is 40, so the remaining work out of total work is 60, this remaining work 60 was done by P with the efficiency of 4, so he takes 15 days to complete remaining work