A and B together can complete a work in 3 days. They start together. But, after 2 days, B left the work. If the work is completed after 2 more days, B alone could do the work in
A). 19 days
B). 13 days
C). 10 days
D). 6 days
6 days
A and B’s 1 day’s work = 1/3
Their 2 day’s work = 1/3 × 2 = 2/3
Remaining work = 1/3
1/3 of the work is finished by A in 2 days
Then, the whole work can be finished by A alone in 3 × 2 = 6 days
So, A’s 1 day’s work = 1/6
Therefore, B’s 1 day’s work = 1/3 – 1/6 = 1/6
Therefore, the whole work can be done B alone in 6 days