 The ratio of efficiency of A is to C is 5:3. The ratio of number of days taken by B is to C is 2:3. A takes 6 days less than C, when A and C completes the work individually. B and C started the work a

Asked on by | Votes 0 | Views: 49 | Tags: quantitative aptitude     | time and work     | Add Bounty

 The ratio of efficiency of A is to C is 5:3. The ratio of number of days taken by B is to C is 2:3. A takes 6 days less than C, when A and C completes the work individually. B and C started the work a

A). 4.5

B).  5

C). 6

D). 9 1/3


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

0 vote
Answered by on | Votes 0 |

6



NA

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (2+1)
Submit:

Other Questions

1.  A and B can do a piece of work in 10 h. B and C can do it in 15 h, while A and C take 12 h to complete the work. B independently can complete the work in

2. A and B do ($\frac{3}{5}$)th part of a work and the rest of the work is completed by C. If A, B and C take the same work for Rs 5000, then what is the share of C (in Rs)?

3. A can do a work in 12 days and B in 24 days. If they work on it together for 4 days, then what fraction of work is left?

4. Peter can do a piece of work in 20 hours and Quagmire can do it in 5 hours. Peter and Quagmire undertook to do it for $1008. With the help of Goldman, they finished the work together in 2 hours. How much money did Goldman get?

5.  A can finish a work in 18 days and B can do the same work in half the time taken by A. Then, working together, what part of the same work they can finish in a day?

6.  A is twice as good a workman as B and together they finish a piece of work in 14 days. The number of days taken by A alone to finish the work is:

7. Mike and Mindy can make paintings in 6 days, Mindy and Josh can make those paintings in 10 days. If Mike, Mindy & Josh together can finish the work in 4 days, then Mike & Josh together will do it in how many days?

8. A and B together can do a piece of work in 9 days. If A does thrice the work of B in a given time, the time A alone will take to finish the work is

9.  A, B and C can do a work in 6, 8 and 12 days respectively doing the work together and get a payment of Rs.1800. What is B’s share?

10.  If A can complete a job in 10 days and along with B he can complete the same job in 6 days, how much of the job remain to be completed if both work for 4 days and A alone works for two more days ?