 A is 30% more efficient than B. How much time will they, working together, take to complete a job which A alone could have done in 23 days?

Asked on by | Votes 0 | Views: 950 | Tags: quantitative aptitude     | time and work     | Add Bounty

 A is 30% more efficient than B. How much time will they, working together, take to complete a job which A alone could have done in 23 days?

A). 13 days

B). 24 days

C). 37 days

D). 45 days


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

-1 vote
Answered by on | Votes -1 |

13 days



The ratio of their efficiency = A : B = 130 : 100 = 13 : 10 

Therefore, the ratio of the time taken by them = 10 : 13 

A takes 23 days = 10 units of ratio 

So, 1 unit of ratio = 23/10 

Time taken by B alone to finish the work = 23/10 ×13 = 29.9 = 30 days 

Therefore, the No. of days taken to finish the work working together = 23 × 30/ 53 

= 13 days

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (4+2)
Submit:

Other Questions

1. A and B can complete a piece of work in 12 and 18 days reapectlvely. A begins to do the work and they work alternatively one at a time for one day each. The whole work will be completed in

2.  A can do a piece of work in 15 days and B in 20 days. How much time will they take to complete the work if they work on alternate days, starting with A ?

3. Azhar is 4 times as good a workman as Balaraj and therefore is able to finish a job in 45 days less than Balaraj. Working together, they can do it in:

4. A and B can do a piece of work in 36 days, B and C can do it in 60 days, A and C can do it in 45 days, C alone can do it in

5. P and Q undertook to do a work for Rs. 7200. P alone could do it in 20 days and Q alone in 12 days. With the assistance of R they finished the work in 5 days. What is the share (in Rs) of R?

6.  If 4 men or 6 boys can finish a work in 20 days. How long will 6 men and 11 boys take to finish the same work?

7. Twenty women can do a work in sixteen days. Sixteen men can complete the same work in fifteen days. The ratio between the capacity of a man and a woman is

8.  16 men or 20 women can finish a work in 25 days. How many days 28 men and 15 women will take to finish this job?

9. Two inlet pipes A & C can fill a tank in 10 hours & 20 hours respectively, operating alone. Outlet pipe B can empty a full tank in 8 hours. Pipe A discharge milk. Whereas pipe C discharges water. The 3 pipes are opened in the order, A, C, C, B, C, A, B. i.e. only pipe A is opened for 1st hour, then only pipe C is opened for the 2nd hour and so on. This continues for 7 hours. Find the ratio of milk to water in the tank after 7 hours.

10. Consider three pipes P, Q and R. The pipes P and Q can fill the cistern in 2 and 2.5 hours respectively. The pipe R can empty the cistern in 1 hour. If these pipes were opened at an interval of half an hour at 6:00am, 6:30am and 7:00am respectively. When the cistern will get empty?