A and B can do a piece of work in 36 days, B and C can do it in 60 days, A and C can do it in 45 days, C alone can do it in

Asked on by | Votes 0 | Views: 41 | Tags: time and work     | quantitative aptitude     | ssc chsl 2012     | Add Bounty

A and B can do a piece of work in 36 days, B and C can do it in 60 days, A and C can do it in 45 days, C alone can do it in
1). 90 days
2). 180 days
3). 120 days
4). 150 days


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

1 vote
Answered by on | Votes 1 |
I think option 2 is the right answer

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (4+4)
Submit:

Other Questions

1. X and Y can complete a work in 5 days. Y and Z can complete the same work in 6 days. Z and X can complete the same work in 15/2 days. In how many days will X, Y and Z together complete the work?

2.  A is twice as good a workman as B and they took 7 days together to do the work B alone can do it in.

3. A tank can be filled by one tap in 6 hours and by another tap in 8 hours. How long will it take to fill the tank, if both the taps are opened together?

4.  'A' can complete a piece of work in 5 days and ' B ' can complete the same piece of work in 10 days. In how many days can 'A' and ' B ' together complete the same work ?

5. A garrison of 150 men is provided with a ration for 25 days. If they have to stay for a period of 5 days more, by what amount they should decrease their consumption?

6. A pipe can fill a tank in 42 minutes. Because of the leak in the tank, it took 14 minutes more to fill the tank. What is the ratio between the time required for the pipe to fill the tank and time required for the leak to empty the tank?

7. Given below are two quantities named A & B. Based on the given information, you have to determine the relation between the two quantities. You should use the given data and your knowledge of Mathematics to choose between the possible answers. Quantity A: A and B together, B and C together and C

8. A can do a certain job in 36 days. When A and B work together, they can do the same job in 9 days. Thus, B is: 

9.  A mason can build a tank in 12 h. After working for 6 h, he took the help of a boy and finished the work in another 5 h. The time that the boys will take alone to complete the work is

10. C is 5 times as productive as B. A takes 60 days to complete a task. If A, B and C work together they can complete the task in 12 days. In how many days can B complete the task if he worked alone?