If A and B together can complete a work in 18 days, A and C together in 12 days and B and C together in 9 days, then B alone can do the work in

Asked on by | Votes 0 | Views: 55 | Tags: time and work     | quantitative aptitude     | ssc section officer 2007     | Add Bounty

If A and B together can complete a work in 18 days, A and C together in 12 days and B and C together in 9 days, then B alone can do the work in
1). 18 days
2). 24 days
3). 30 days
4). 40 days


Share on Facebook      Share on Whatsapp       Share on Twitter




2 answers

0 vote
Answered by on | Votes 0 |
option 2 : 24 days is correct

Join Telegram Group




2 vote
Answered by on | Votes 2 |
54




Answer This Question

Name:
Email:
Answer :
Sum of (1+1)
Submit:

Other Questions

1. A skilled, a half skilled and an unskilled labourer work for 7,8 and 10 days respectively and they together get Rs. 369 for their work. If the ratio of their each day's work is $\frac{1}{3}:\frac{1}{4}:\frac{1}{6}$, then how much does the trained labourer get ( in rupees ) ?

2. A and B can do a plece of work in 28 and 35 days respectively. They began to work together but A leave after sometime and B completed remaining work in 17 days. After how many days did A leave ?

3.  Twenty four men can do a work in 35 days. How many men are required to complete the work in 21 days?

4. 40 men can complete a work in 18 days. Eight days after they started working together, 10 more men Joined them . How many days will they now take to complete the remaining work ?

5. 2 men and 3 women undertook a piece of work for Rs. 12,000. 2 men can do the work in 12 days and 3 women can do the same work in 15 days. With the assistance of 5 children, they finished the work in 5 days. What is the share of 1 child?

6.  Twelve men and six women together can complete a piece of work in four days. The work done by a women in one day is half the work done by a man in one day. If 12 men and six women started working and

7.  A and B can do a piece of work in 3 days, B and C in 4 days, C and A in 6 days. How long will C take to do it?

8. 3 men and 7 women can do a Job In 5 days, while 4 men and 6 women can do it in 4 days. The number of days required for a group of 10 women working together, at the same rate as before, to finish the same job is :

9. Five women can do a work in thirty six days. If the ratio between the capacity of a man and a woman is 3 : 1, then find how may days it will take 5 men to complete the same work?

10. If 15 person can do a job in 30 days, then 30 persons with twice the efficiency can do the same job in how many days?