A can do one and a half as much of a work which B can do in one day. B alone can do a piece of work in 18 days. They together can finish that work in

Asked on by | Votes 15 | Views: 382 | Tags: time and work     | quantitative aptitude     | ssc multitasking 2013     | Add Bounty

A can do one and a half as much of a work which B can do in one day. B alone can do a piece of work in 18 days. They together can finish that work in
1). $10\frac{1}{5}$ days
2). $11\frac{1}{5}$ days
3). $5\frac{1}{5}$ days
4). $7\frac{1}{5}$ days


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

39 vote
Answered by on | Votes 39 |
option 4 : seems correct

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (1+5)
Submit:

Other Questions

1. If 80 persons can finish a work within 16 days by working 6 hours a day. the number of hours a day, should 64 persons work to finish that very job within 15 days is:

2. Anju and Bablu can do a job together in 18 days. Anju is \(3\frac{2}{3}\) times more efficient than Bablu. The same job can be done by Bablu alone in

3. A can do a piece of work in 8 days and B can do it in 10 days separately. How many days would it take for both A and B to finish the same work together?

4. Amar can complete a work in 30 days and Raman can complete the same work in 15 days. If both of them work together, then in 4 days what percent of the total work will be completed?

5.  A can do a piece of work in 60 days. He worker for 15 days and then B alone finishes the remaining work in 30 days. The two together can finish the work in

6.  A and B can do a work in 12 days, B and C in 30 days and C and A in 36 days. In how many days will the work be completed, if all three of them work together?

7. Three people P, Q and R have been assigned a work. P and Q can complete a work in 15 days and Q and R can complete a work in 18 days and all of them can complete the whole work in 12 days, then find the number of days in which P and R alone can do the whole work?

8. Prabodh has done $\frac{1}{2}$ of a job in 30 days, Sapan completes the rest of the job in 45 days. In how many days can they together do the job?

9.  A can finish a work in 15 days, B in 20 days and C in 25 days. All these worked together and earned Rs. 4700. The share of C is

10.  Ashokan is thrice as good a workman as Nitin and is therefore able to finish a piece of work in 40 days less than Nitin. Find the time in which they can do it working together.