20 men or 24 women can complete a piece of work in 20 days. If 30 men and 12 women undertake to complete the work, the work will be completed in

Asked on by | Votes 0 | Views: 82 | Tags: time and work     | quantitative aptitude     | ssc statistical investigator 2010     | Add Bounty

20 men or 24 women can complete a piece of work in 20 days. If 30 men and 12 women undertake to complete the work, the work will be completed in
1). 10 days
2). 12 days
3). 15 days
4). 16 days


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

0 vote
Answered by on | Votes 0 |
Answer for this question is option 1

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (1+3)
Submit:

Other Questions

1. 45 men or 60 boys can do a piece of work in 20 days. How many days will 15 men and 20 boys take to complete the work?

2. A can complete a work in 6 days while B can complete the same work in 12 days. If they work together and complete it, the portion of the work done by A is

3. A can do 50% of the job in 16 days, B can do 1/4th of the job in 24 days. In how many days can they do 3/4th of the job working together?

4. Two pipes P and Q can fill the tank in 28 hours. Had they been opened separately, P would have taken twice the time as Q to fill the cistern. How much time will Q take to fill the cistern alone?

5.  A is half good a work man as B and together they finish a job in 14 days. In how many days working alone B finish the job?

6.  36 workers can reap a field in 6 days. If the work is to be completed in 4 days, the extra workers required are

7. A and B can do a piece of work in 30 days while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work ?

8. A bucket can be filled by a pipe in 10 minutes and by another pipe in 40 minutes. Both the pipes are kept open for 5 minutes and then first pipe is closed. After this, how much time will be required to fill the complete bucket?

9. Two workers A and B are engaged to do a piece of work. A working alone would take 8 hours more to complete the work than when work together. If B worked alone, would take $4\frac{1}{2}$ hours more than when work together. The time required to finish the work together is

10. A does 75% of a work in 25 days. He then calls in B and they together finish the remaining work in 5 days. How long B alone would take to do the whole work?