Parimal has done 1/4 th of a job in 10 days, Salim completes the rest of the job in 20 days. In how many days can they together do the job?

Asked on by | Votes 31 | Views: 761 | Tags: ssc     | ssc chsl     | ssc chsl tier 1     | ssc chsl 2016     | ssc chsl 17 01 2017     | time and work     | quantitative aptitude     | Add Bounty

Parimal has done 1/4 th of a job in 10 days, Salim completes the rest of the job in 20 days. In how many days can they together do the job?
1). 8 days
2). 24 days
3). 12 days
4). 16 days

SSC CGL Books


Share on Facebook      Share on Whatsapp       Share on Twitter




2 answers

2 vote
Answered by on | Votes 2 |
I think option 4 is the right answer

Join Telegram Group




39 vote
Answered by on | Votes 39 |

Let total work to be done $= 80$ units

Work done by Parimal in 10 days $= \frac{1}{4} \times 80 = 20$ units

Parimal's efficiency $= \frac{20}{10} = 2$ units/day

Remaining work $= 80 - 20 = 60$ units

Salim completes $60$ units in $20$ days

=Salim's efficiency $= \frac{60}{20} = 3$ units/day

(Parimal + Salim)'s 1 day's work $= 2 + 3 = 5$ units/day

$\therefore$ Time taken by them together to do the job $= \frac{80}{5} = 16$ days

Accepted Answer




Other Questions

1. The ratio of efficiencies of P, Q and R is 4 : 3 : 8. In how much time can they finish a work together if Q can finish it alone in 4.5 hours? (in minutes)

2. U, V and W together can make a chair in 20 minutes. U and V together can make it in 25 minutes. How much time will (in minutes) W alone take to make the chair?

3. Ajit is two times as good a workman as Badrinath and therefore is able to finish a job in 30 days less than Badrinath. Working together, they can do it in

4.  X completes a job in 2 days and Y completes it in 3 days and Z takes 4 days to complete it. If they work together and get Rs. 3900 for the job, then how much amount does Y get?

5. 18 men or 36 boys working 6 hours a day can plough a field in 24 days. In how many days will 24 men and 24 boys working 9 hours a day plough the same field ?

6. A garrison of 500 men had provisions for 27 days. After 3 days, a reinforcement of 300 men arrived. The remaining food will now last for how many days?

7.  A works twice as fast as B. if both of them can together finish a piece of work in 12 days, then B alone can do it in

8.  A and B can finish a work in 16 days while A alone can do the same work in 24 days. In how many days B alone will complete the work?

9. Two pipes can fill a tank in 12 hours and 24 hours respectively. The pipes are opened simultaneously and it is found that due to leakage in the tank, it took 2 hours more to fill the tank. When the tank is completely full, in what time will the leak empty it?

10.  A works alone, he would take 4 days more to complete the job than if both A and B worked together. If B worked alone, he would take 16 days more to complete the job than if both A and B work together.