A can do a work in 4 days and B can do the same work in 5 days. The contract for the work is Rs 945. How much shall A get if both of them work together ?
A). Rs. 505
B). Rs. 525
C). Rs. 535
D). Rs. 555
'A'can do a piece of work in 10 days and'B'can do the same work in 15 days. How long will it take ifboth work together ?
A). 6 days
B). 7 days
C). 8 days
D). 9 days
A alone can finish a work in 10 days which B alone can finish in 15 days. If they work together and finish it, then out of a total wages of Rs.3000, A will get:
A). Rs.1200
B). Rs.1500
C). Rs. 1800
D).
Rs.2000
A can do 1/4th part of the work in 10 days, B can do 40% of the work in 40 days and C can do 1/3rd of the work in 13 days. Who will complete the work first?
A). A
B). B
C). C
D). A and C both
A does 4/5th of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?
A). 23 days
B). 37 days
C).
37 ½ days
D). 40 days