ExamCompetition Forum Question Papers Ask A Question Mock Test Learn & Earn Sign Up Login Menu



24 vote

A, B and C can independently finish a piece of work in 18 days, ?x? days and 27 days respectively. A and C started working together and after 6 days B replaced both of them. If B could finish the remaining work in 16 days, what is the value of ?x? ?

Asked on by | Votes 24 | Views: 581 | Tags: sbi     | sbi clerk     | sbi clerk 05 june 2016     | time and work     | quantitative aptitude     | Add Bounty



A, B and C can independently finish a piece of work in 18 days, ?x? days and 27 days respectively. A and C started working together and after 6 days B replaced both of them. If B could finish the remaining work in 16 days, what is the value of ?x? ?
1). 32
2). 36
3). 34
4). 40


Share on Facebook      Share on Whatsapp       Share on Twitter




2 answers

36 vote
Answered by on | Votes 36 |
Solution

(A + C)'s 1 day's work = $\frac{1}{18} + \frac{1}{27}$

= $\frac{3 + 2}{54} = \frac{5}{54}$

=> (A + C)'s 6 day's work = $\frac{5}{54} \times 6$

= $\frac{5}{9}$

=> Remaining work = $1 - \frac{5}{9} = \frac{4}{9}$

Acc to ques,

=> $\frac{16}{x} = \frac{4}{9}$

=> $x = \frac{16 \times 9}{4}$

=> $x = 4 \times 9 = 36$ days

Join Telegram Group




4 vote
Answered by on | Votes 4 |
Solution

(A + C)'s 1 day's work = $\frac{1}{18} + \frac{1}{27}$

= $\frac{3 + 2}{54} = \frac{5}{54}$

=> (A + C)'s 6 day's work = $\frac{5}{54} \times 6$

= $\frac{5}{9}$

=> Remaining work = $1 - \frac{5}{9} = \frac{4}{9}$

Acc to ques,

=> $\frac{16}{x} = \frac{4}{9}$

=> $x = \frac{16 \times 9}{4}$

=> $x = 4 \times 9 = 36$ days




Answer This Question

Name:
Email:
Answer :
Sum of (5+4)
Submit:

Other Questions

1. can finish a work in 18 days and B in 36 days. If they work on it together for 9 days, then what percent of work is left?

2. A is 30% more efficient than B, and can alone do a work in 23 days. The number of days, in which A and B, working together can finish the Job is

3. A can do a certain job in 36 days. When A and B work together, they can do the same job in 9 days. Thus, B is: 

4.  A, B and C can complete a piece of work in 24,6 and 12 days respectively.Working together, they will complete the same work in:

5. Two pipes P and Q can fill the tank alone in 60 and 90 hours respectively. If they are opened together, then in how many hours will the tank be filled?

6.  12 men take 36 days to do a work while 12 women complete 3/4th of the same work in 36 days. In how many days 10 men and 8 women together will complete the same work?

7. If 80 persons can finish a work within 16 days by working 6 hours a day. the number of hours a day, should 64 persons work to finish that very job within 15 days is:

8.  A can do a piece of work in 12 days, while B can do it in 8 days with the help of C, they finish the work in 4 days. Then C alone can do the work in

9. A certain number of men can do a work in 60 days. If there were eight more men, it could be completed in 10 days less . How many men were there in the beginning?

10. X, Y and Z can do a piece of work in 60, 90 and 180 days respectively. In how many days X can do the work if he is assisted by Y and Z on every third day?