Two labourers A and B are paid a total of Rs. 1120 per day. If A is paid 180 percent of what is paid to B, how much (in Rs) is B paid?

Asked on by | Votes 0 | Views: 152 | Tags: time and work     | ssc cgl tier 1 18 08 2017 shift 3     | ssc cgl tier 1     | ssc cgl     | quantitative aptitude     | ssc cgl tier 1 2017     | ssc cgl 2017     | Add Bounty

Two labourers A and B are paid a total of Rs. 1120 per day. If A is paid 180 percent of what is paid to B, how much (in Rs) is B paid?
1). 400
2). 720
3). 500
4). 620


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

3 vote
Answered by on | Votes 3 |
i think option 1 is correct

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (4+2)
Submit:

Other Questions

1.  Gopal complete a work in 8 hrs. Jaiprakash complete it in 5 hours. If both work together, they will complete it in how many hours ?

2. If 20 men can build a wall 25 meters long in 4 days, what length of a similar wall can be built by 30 men in 6 days?

3.  If 5 men or 8 women can do a work in 44 days, how long will 10 men and 6 women take to complete the work together ?

4. A piece of work was finished by A, B and C together. A and B together finished 60% of the work and B and C together finished 70% of the work. Who among the three is most efficient?

5. If 10 men or 20 women or 40 children can do a piece of work in 7 months, then 5 men. 5 women and 5 children together can do half of the work in :

6. A project requires 12 women to complete it in 16 days. 12 women started working and after a few days from the start of the project, 4 women left. If the remaining project was completed in 18 days, in how many days the whole project was completed?

7. If 80 persons can finish a work within 16 days by working 6 hours a day. the number of hours a day, should 64 persons work to finish that very job within 15 days is:

8. A is 30% more efficient than B, and can alone do a work in 23 days. The number of days, in which A and B, working together can finish the Job is

9. A alone can do a work in 20 days. B is 25% more efficient than A. A and B started working and worked for 4 days. If C alone completed the remaining job in 22 days. How many days C alone takes to complete the entire job?

10. If 4 men or 6 women can do a piece of work in 12 days working 7 hours a day; how marry days will it take to complete a work twice as large with 10 men and 3 women working together 8 hours a day?