 24 men complete a work in 12 days. In how many days can 18 men complete the same piece of work ?

Asked on by | Votes 0 | Views: 15 | Tags: quantitative aptitude     | time and work     | Add Bounty

 24 men complete a work in 12 days. In how many days can 18 men complete the same piece of work ?

A). 16 days

B). 17 days

C). 18 days

D). 19 days


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

0 vote
Answered by on | Votes 0 |

16 days



Because, 24 men can complete 1 work in 12 days.
Therefore, 1 man can complete 1 work in 12 x 24 days
Therefore, 18 men can complete 1 work in12 x 24/18 = 16 days

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (5+1)
Submit:

Other Questions

1. Gaurav is 4 times as good a workman as Vaibhav and therefore is able to finish a job in 60 days less than Vaibhav. How many days both will take finish the same task?

2.  A can do a piece of work in 12 days, while B can do it in 8 days with the help of C, they finish the work in 4 days. Then C alone can do the work in

3. P and Q together can do a job in 6 days. Q and R can finish the same job in $\frac{60}{7}$ days. P started the work and worked for 3 days. Q and R continued for 6 days. Then the difference of days in which R and P can complete the job is

4. A, B and C can do a piece of work in 10 days, 20 days and 15 days respectively, working alone. How soon can the work be done if A assisted by B and C on alternate days?

5.  A and B together can plough a field in 10 hours but by himself A requires 15 hours. How long would B take to plough the same field?

6. Pipe A can fill a tank in 12 hours and Pipe B can fill the tank in 18 hours. If both the pipes are opened on alternate hours and if pipe B is opened first, then in how much time (in hours) the tank will be full?

7. A and B undertook a piece of work for Rs.9000. A alone could do it in 16 days and B alone in 24 days. With the assistance of C they finished the work in 8 days. Then C’s share in the total money is?

8. C is 5 times as productive as B. A takes 60 days to complete a task. If A, B and C work together they can complete the task in 12 days. In how many days can B complete the task if he worked alone?

9. Ramu and Shamu together earn Rs. 500 per day, while Shamu and Kalu together earn Rs. 450 per day. If Shamu, Ramu and Kalu, working together earn Rs. 700 per day, then calculate the ratio of one day’s work of Shamu and Kalu?

10.  If 12 men and 16 boys can do a piece of work in 5 days and 13 men together will 24 boys can do it in 4 days. Compare the daily work done by a man with that of a boy.