 A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work is done by A in

Asked on by | Votes 0 | Views: 26 | Tags: quantitative aptitude     | time and work     | Add Bounty

 A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work is done by A in

A). 4 days

B). 7 days

C). 10 days

D). 13 days


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

0 vote
Answered by on | Votes 0 |

10 days



10 days

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (4+1)
Submit:

Other Questions

1. B is 50% more efficient than A & 20% more efficient than C. If B can complete a work in 20 days, how many days will A & C together take to compete the same work.

2. A group experiment was conducted. If 2 students of Class 12 and 1 student of class 11 can complete the experiment in 14 minutes while 4 students of class 11 and 2 students of class 12 can complete it in 8 minutes. If one Class 12 student gets Rs. 600 for doing the experiment, how much should a class 11 student get?

3. M takes 60% more time than N to complete a wall. If together they complete the wall in 24 days, then how many days will N alone take to complete it?

4.  A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days A alone can finish the remaining work?

5.  4 men, 6 women and 8 children can complete a work in 11 days. A woman does double the work a man does and a child does the half the work a man does. How many women alone can do the same work in 11 day

6.  A, B & C can complete a piece of work in 24, 6 12 days. Respectively, working together, they will complete the same wok in -

7. Ravi does half as much work as Rahim in four-fifth of the time. If together they take 40 days to complete the work, how much time shall Ravi take to do it?

8. A and B together do a job in 15 days and A alone could do the same job in 20 days. How many days would B take to do half the job if he worked alone?

9. A tap can fill a tank in 36 minutes and another can empty it in 18 minutes. If the tank is already ½ full and both the taps are opened together, will the tank be filled or emptied? How long will it take before the tank is either filled completely or emptied completely, as the case may be?

10. If A and B together can finish a piece of work in 20 days B and C in 10 days and C and A in 12 days, then A, B, C jointly can finish the same work in