 A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days A alone can finish the remaining work?

Asked on by | Votes 0 | Views: 30 | Tags: quantitative aptitude     | time and work     | Add Bounty

 A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days A alone can finish the remaining work?

A). 6 Days

B). 5 Days

C). 4 Days

D). 8 Days


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

0 vote
Answered by on | Votes 0 |

6 Days



NA

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (4+3)
Submit:

Other Questions

1. Anju and Bablu can do a job together in 18 days. Anju is \(3\frac{2}{3}\) times more efficient than Bablu. The same job can be done by Bablu alone in

2. Yesterday Shweta completed 300 units of work at the rate of 15 units per minute. Today she completed the same units of work but her speedwas 40% faster than yesterday. What is the approximate difference in the time she took to complete the work yesterday and the time she took today ?

3. Rahul and Ravi undertook to do a piece of work for Rs. 9000. Rahul alone could do the work in the 16 days and Ravi in 24 Days. With the assistance Kamlesh, they finished the work in 8 days. How much money should be given to Kamlesh?

4.  A is thrice as good work than as B. Together they can finish a work in 6 days.In how many days A alone do the work?

5. Vijay can do a work in 8 hours. Vijay and Puneet together can do the same work in 6 hours. Puneet and Sachin together can do the same work in 4 hours. Sachin alone can complete the same work in how many hours?

6. Three men A, B and C working together can do a Job in 6 hours less time than A alone, in 1 hour less time than B alone and in one half the time needed by C when working alone.Then A and B together can do the Job in

7. Given below are two quantities named A & B. Based on the given information, you have to determine the relation between the two quantities. You should use the given data and your knowledge of Mathematics to choose between the possible answers. Quantity A: Four herdsmen rented a pasture. A&#

8. Ramu and Shamu together earn Rs. 500 per day, while Shamu and Kalu together earn Rs. 450 per day. If Shamu, Ramu and Kalu, working together earn Rs. 700 per day, then calculate the ratio of one day’s work of Shamu and Kalu?

9. A,B and C together earn Rs. 450 per day, while A and C together earn Rs.310 and Band C together earn Rs.260. The daily earning of C is 

10.  6 women can complete a piece of work in 10 days, whereas 10 children alone take 15 days to complete the same piece of work. How many days will 6 women and 10 children together take to complete the pie