A can do a piece of work in 12 days and B can do it in 18 days. They work together for 2 days and then A leaves. How long will B take to finish the remaining work ?

Asked on by | Votes 0 | Views: 41 | Tags: time and work     | quantitative aptitude     | ssc cgl tier 1 1999     | Add Bounty

A can do a piece of work in 12 days and B can do it in 18 days. They work together for 2 days and then A leaves. How long will B take to finish the remaining work ?
1). 6 days
2). 8 days
3). 10 days
4). 13 days


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

2 vote
Answered by on | Votes 2 |
13 days : - is correct hence option 4

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (4+4)
Submit:

Other Questions

1. Water flows into a tank which is 200 m long and 150 m wide, through a pipe of cross-section 0.3 m × 0.2 m at 20 km/hour. Then the time (in hours) for the water level in the tank to reach 8 m is

2. 4 men can complete a piece of work in 3 days. 6 women can complete the same piece of work in 3 days, whereas 3 children can complete the same piece of work in 8 days. 3 women and 4 children worked together for 1 day. If only men were to finish the remaining work in 1 day, how many total men would be required?

3.  A and B can do a piece of work in 15 days. B and C can the same work in 10 days and A and C can do the same in 12 days. Time taken by A, B and C together to do the job is

4.  4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days. In how many days will 10 women complete it?

5. A, B and C are employed to do a piece of work for Ra. 5,290. A and B together are supposed to do $\frac{19}{23}$ of the work and B and C together $\frac{8}{23}$ of the work. Then A should be paid

6.  A can do a work in 15 days and B in 20 days. If they work on it together for 4 days then the fraction of the work that is left is?

7. Three persons A, B and C can do a piece of work 20, 15 and 30 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?

8.  10 men can complete a work in 7 days. But 10 women need 14 days to complete the same work. How many days will 5 men and 10 women need to complete the work?

9. 45 men or 60 boys can do a piece of work in 20 days. How many days will 15 men and 20 boys take to complete the work?

10.  A can do a work in 4 days and B can do the same work in 5 days. The contract for the work is Rs 945. How much shall A get if both of them work together ?