A can do a work in 4 days and B can do the same work in 5 days. The contract for the work is Rs 945. How much shall A get if both of them work together ?
A). Rs. 505
B). Rs. 525
C). Rs. 535
D). Rs. 555
Rs. 525
A's share = 945/(4 + 5) x 5 = 945 x 5/9 = 525