A certain number of men complete a piece of work in 60 days.If there were 8 men more, the work could be finished in 10 days less. The number of men originally was
A certain number of men complete a piece of work in 60 days.If there were 8 men more, the work could be finished in 10 days less. The number of men originally was 1). 30 2). 40 3). 32 4). 36
1 answers
Answered by
Guest on
2018-03-05 02:19:10 | Votes
0 |
#
This question was asked some where in previous year papers of ssc, and correct answer was 40
Join Telegram Group
Other Questions
1. A and B can do a piece of work in 36 days, B and C can do it in 60 days, A and C can do it in 45 days, C alone can do it in
2. If 5 men or 9 ladies can complete a bit of work in 19 days, 3 men and 6 ladies will do likewise work in
3. A and B can do a work in 12 days, B and C in 15 days, C and A in 20 days. if A, B and C work together, In how many days they will complete the work?
4. 'A'can do a piece of work in 10 days and'B'can do the same work in 15 days. How long will it take ifboth work together ?
5. 2 men and 3 women can do a piece of work in 10 days while 3 men and 2 women can do the same work in 8 days. Then , 2 men and 1 women can do the same work in
6. A can do 75% of a job in 18 days and B can do 25% of the job in 12 days. If they work on it together, in how many days can they do 75% of the job?
7. A can do a piece of work in 6 days working 8 hours a day while B can do the same work in 4 days working 10 hours a day. If the work has to be completed in 5 days, so how many hours do they need to work together in a day
8. A and B together can do a work in 6 days. If A alone can do the work in 10 days then in how many days can B alone do it ?
9. A complete 80% of a work in 20 days. Then B also foins and A and B together finish the remaining work in 3 days. How many days will be required for B if he al0one complete the work?
10. Anil is twice as good as workman as Bimal and together they finish a piece of work in 9 days. In how many days will Anil alone finish the work?