 A complete 80% of a work in 20 days. Then B also foins and A and B together finish the remaining work in 3 days. How many days will be required for B if he al0one complete the work?

Asked on by | Votes 0 | Views: 23 | Tags: quantitative aptitude     | time and work     | Add Bounty

 A complete 80% of a work in 20 days. Then B also foins and A and B together finish the remaining work in 3 days. How many days will be required for B if he al0one complete the work?

A). 35 Days

B). 30 Days

C). 37 1/2 Days

D). 25 Days


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

0 vote
Answered by on | Votes 0 |

37 1/2 Days



NA