24 men can do a piece of work in 17 days.How many men will be able to do it in 51 days ?
24 men can do a piece of work in 17 days.How many men will be able to do it in 51 days ?
1). 8
2). 10
3). 12
4). 6
SSC CGL Books
1 answers
Answered by
Guest on
| Votes
2 |
#
Correct answer is: option 1
Join Telegram Group
Other Questions
1. A is twice as fast as B. If B alone can do a piece of work in 30 days, in what time can A and B together complete the work?
2. Ram and Hari can cut 12 kgs nuts in 2 days. After 5 days, Hari left the work. Ram took 8 more days to cut the rest of the nuts. If total of 58 kgs of nuts
were cut, the time taken by Hari to cut 10 kg of nuts is
3. Machine A produces nuts at a uniform rate of 23056 every 1048 seconds, and machine B produces nuts at a uniform rate of 91168 every 3256 seconds. If the two machines run simultaneously, how many seconds will it take them to produce a total of 1800 nuts?
4. A and B together can do a work in 12 days. B and C together do it in 15 days. If A's efficiency is twice that of C, then the days required for B alone to finish the work is
5. If a man earns Rs. 2000 for his first 50 hours of work in a week and is then paid one and a half times his regular hourly rate for any additional hours, then the hours must he work to make Rs. 2300 in a week is
6. A can do a piece of work in 1o days, B can do the same work in 15 days. They work for 5 days. The rest of work finished by C in 2 days. If they get Rs 1500 for the whole work, the daily wages of B and
7. If 36 persons are engaged on a piece of work, the work can be completed in 40 days. After 32 days, only 3/4 th of the work was completed. How many more persons are required to complete the work on time?
8. A, B and C can do a work separately in 16, 32 and 48 days respectively. They started the work together but B left off 8 days and C six days before the completion of the work. In what time is the work finished ?
9. 28 men can complete a piece of work in 21 days. How many more men must be hired to complete the work in 14 days ?
10. Pipes A and B can fill a tank in 5 hours and 20 hours respectively. If both pipes are opened then, how much time (in hours) it will take to fill the tank?