A does 4/5 of work in 20 days. Then A calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?
A). 32 Days
B). 37 1/2 Days
C). 35 Days
D). 40 Days
A complete 80% of a work in 20 days. Then B also foins and A and B together finish the remaining work in 3 days. How many days will be required for B if he al0one complete the work?
A). 35 Days
B). 30 Days
C). 37 1/2 Days
D). 25 Days
A can do a piece of work in 1o days, B can do the same work in 15 days. They work for 5 days. The rest of work finished by C in 2 days. If they get Rs 1500 for the whole work, the daily wages of B and
A). Rs. 200
B). 225 Rs.
C). 230 Rs.
D). 210 Rs.
4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days. In how many days will 10 women complete it?
A). 40 Days
B). 30 Days
C). 35 Days
D). 45 Days
10 men can complete a work in 7 days. But 10 women need 14 days to complete the same work. How many days will 5 men and 10 women need to complete the work?
A). 5 Days
B). 6 Days
C). 7 Days
D). 8 Days