Three men can complete a piece of work in 6 days. Two days after they started the work. 3 more men Joined them. How many days will they take to complete the remaining work ?

Asked on by | Votes 0 | Views: 32 | Tags: time and work     | quantitative aptitude     | ssc chsl 2013     | Add Bounty

Three men can complete a piece of work in 6 days. Two days after they started the work. 3 more men Joined them. How many days will they take to complete the remaining work ?
1). 1 days
2). 2 days
3). 3 days
4). 4 days


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

0 vote
Answered by on | Votes 0 |
Hello, 2 days is correct

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (4+1)
Submit:

Other Questions

1. Ramu and Shamu together earn Rs. 500 per day, while Shamu and Kalu together earn Rs. 450 per day. If Shamu, Ramu and Kalu, working together earn Rs. 700 per day, then calculate the ratio of one day’s work of Shamu and Kalu?

2. If 10 men or 20 boys can make 260 mats in 20 days, then how many mats will be made by 8 men and 4 boys in 20 days?

3. A, B and C can complete a work in 10, 12 and 15 days respectively. A left the work 5 days before the work was completed and B left 2 days after A had left. Number of days required to complete the whole work is :

4. Two pipes P and Q can fill a tank in 3 hrs. and 4 hrs. respectively. If both pipes are opened together, then after what time, should P be closed so that the tank is full in 2 hrs. from the start

5. A, B and C can complete a piece of work in 24,5 and 12 days respectively. Working to gether, they will complete the same work in :

6.  A can do a bit of work in 10 days and B can do it in 20 days. They begin the work together . Be that as it may, following 5 days, A leaves off. B will do the remaining work in

7. A swimming pool has 3 pipes to drain off the water. The first two pipes A and B, operating simultaneously, can empty the pool in 9/16 the time than that taken by C alone. Pipe A, working alone, takes one third the time taken by pipe B. All of them together take 2 hrs 24 minutes to empty the pool. Time taken by pipe A to empty the pool in hours is

8. A can complete a work in 6 days while B can complete the same work in 12 days. If they work together and complete it, the portion of the work done by A is

9.  A is thrice as efficient as B and is, therefore, able to finish a piece of work 10 days earlier than B. In how many days A and B will finish it together?

10.  A and B can do a piece of work in 30 days, while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take t