A can finish a work in 24 days. B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in :

Asked on by | Votes 0 | Views: 31 | Tags: time and work     | quantitative aptitude     | ssc cgl tier 1 2003     | Add Bounty

A can finish a work in 24 days. B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in :
1). 5 days
2). 6 days
3). 10 days
4). $10\frac{1}{2}$ days


Share on Facebook      Share on Whatsapp       Share on Twitter




1 answers

1 vote
Answered by on | Votes 1 |
10 days

Join Telegram Group




Answer This Question

Name:
Email:
Answer :
Sum of (5+4)
Submit:

Other Questions

1. If 3 men or 6 women can do a piece of work in 16 days, in how many days can 12 men and 8 women do the same piece of work?

2. Jack and Finn can finish a work together in 6 hours, while Finn alone can do it in 10 hours. What is the ratio of efficiencies of Jack and Finn?

3.  A and B can do a job together in 7 days. A is 13/4 times as efficient as B. The same job can be done by A alone in

4.  If A, B and C together can finish a piece of work in 4 days. A alone in 12 days and B in 18 days, then C alone can do it in?

5. A certain number of persons can complete a piece of work in 55 days. If there were 6 persons more, the work could be finished in 11 days less. How, many persons were originally there ?

6.  If 12 men and 16 boys can do a piece of work in 5 days and 13 men together will 24 boys can do it in 4 days. Compare the daily work done by a man with that of a boy.

7.  2 men can complete a work in 6 days. 2 women can complete the same work in 9 days, whereas 3 children can complete the same in 8 days. 3 women & 4 children worked together for 1 day. If only men were

8.  A and B can do a piece of work in 30 days, while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take t

9. P can do a work in 10 days. Q can do the same work in 15 days. If they work together for 5 days, how much of the work will they complete?

10. A does 30% of a work in 30 days. He then calls in B and they together finish the remaining work in 20 days. How long B alone would take to do the whole work?