The Public Work Department, Divisional Officer normally makes the payment to the contractor through the mode of
1). Cash
2). Transfer of money in the contractor accounts
3). Cheque book
4). Digital payment
The type of tender work which is generally used for certain specialised work for which there are very limited firms available is
1). Open Tender
2). Limited Tender
3). Single Tender
4). Percentage Rate Tender
The thickness of R.B. lintel and slab with 3 flat standard brick is
1). 10 cm
2). 15 cm
3). 30 cm
4). 45 cm
The value of property during its useful life based on purchase value and depreciations etc. is known as:
1). Junk value
2). Salvage value
3). Scrap value
4). Book value
The change in cost of built-up facilities with the change in size of the project of similar type is known as
1). Time reference cost estimate
2). Cost capacity factor
3). Life cycle cost
4). Unit cost estimate