ExamCompetition Forum Question Papers Ask A Question Mock Test Learn & Earn Sign Up Login Menu

Estimating Practice Questions & Answers

15 vote

The sanction of the detailed estimate, design calculations, quantities of works, rates and cost of the work by the competent authority of the Engineering Department is known as ________.

Asked on by | Votes 15

The sanction of the detailed estimate, design calculations, quantities of works, rates and cost of the work by the competent authority of the Engineering Department is known as ________.
1). Expenditure sanction
2). Administrative approval
3). Technical sanction
4). None of the above

0 vote

The amount of money that should be levied upon contractor due to breach of terms and conditions of contract as for not maintaining the progress, for delay in completion, for bad work is called

Asked on by | Votes 0

The amount of money that should be levied upon contractor due to breach of terms and conditions of contract as for not maintaining the progress, for delay in completion, for bad work is called
1). Penalty
2). Liquidated damage cost
3). Unliquidated damage cost
4). None of the above

18 vote

The plan of a building is in the form of a rectangle with center line dimensions of outer walls as 12.6 m × 17.6 m. The thickness of the wall in superstructure is 40 cm, the plinth area of the building will be

Asked on by | Votes 18

The plan of a building is in the form of a rectangle with center line dimensions of outer walls as 12.6 m × 17.6 m. The thickness of the wall in superstructure is 40 cm, the plinth area of the building will be
1). 210 m2
2). 234 m2
3). 247 m2
4). 284 m2

0 vote

The power to appropriate and re-appropriate funds to meet the expenditure on public works are vested in:

Asked on by | Votes 0

The power to appropriate and re-appropriate funds to meet the expenditure on public works are vested in:
1). Superintendent Engineer
2). Executive Engineer
3). Chief Engineer
4). Assistant Engineer

49 vote

Deduction at the L-junction of wall for total length of the central line is __________.

Asked on by | Votes 49

Deduction at the L-junction of wall for total length of the central line is __________.
1). half the thickness of wall
2). no reduction
3). thickness of wall
4). twice the thickness of wall